13530 W MORRISON ST 91423
Certificate Information: 13530 W MORRISON ST 91423
- Application / Permit
- 26014-10000-00209
- Plan Check / Job No.
- B26LA01852
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE PATIO COVER AND 12'-8" X 13'-2" BEDROOM EXTENSION WITH NEW W.I.C. AND BATHROOM. CONST. PER ENGINEERING
- Permit Issued
- Issued on 2/5/2026
- Issuing Office
- Current Status
- Issued on 2/5/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/20/2026 | APPLICANT |
| Assigned to Plan Check Engineer | 1/23/2026 | LAWRENCE QUIRANTE |
| Corrections Issued | 1/24/2026 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 1/27/2026 | APPLICANT |
| Applicant returned to address corrections | 2/3/2026 | JONATHAN PLATERO |
| Applicant returned to address corrections | 2/4/2026 | KELVIN CHUONG |
| Plan Check Approved | 2/5/2026 | CRISTINA SALAZAR |
| Issued | 2/5/2026 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/30/2026 | JEFF LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 2/2/2026 | JEFF LOREDO |
Contact Information
| Contractor | Ene Builders; Lic. No.: 1113906-B | 21434 WYANDOTTE STREET CANOGA PARK, CA 91303 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | PO BOX 40237 DOWNEY, CA 90239 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/3/2026 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 3/11/2026 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 3/11/2026 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 3/18/2026 | Partial Approval | MISAEL ESPARZA |
| ELECTRICAL-Rough | 3/18/2026 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 3/18/2026 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 3/18/2026 | Not Ready for Inspection | MISAEL ESPARZA |
| Rough-Elec/Plmb/HVAC | 3/18/2026 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 3/25/2026 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 3/25/2026 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 3/25/2026 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 3/25/2026 | Approved | MISAEL ESPARZA |
| Shower Pan | 3/25/2026 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 3/27/2026 | Approved Pending GreenApproval | MISAEL ESPARZA |
| ELECTRICAL-Rough | 3/27/2026 | Approved | MISAEL ESPARZA |
| Insulation | 3/27/2026 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 3/27/2026 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 4/2/2026 | Partial Approval | RAUL OLAGI |
| Drywall Nailing | 4/27/2026 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 4/27/2026 | Not Ready for Inspection | MISAEL ESPARZA |
| Interior/Exterior Lathing | 4/29/2026 | Approved | MISAEL ESPARZA |