1945 1/2 W LEIGHTON AVE 90062
Certificate Information: 1945 1/2 W LEIGHTON AVE 90062
- Application / Permit
- 26014-10000-00195
- Plan Check / Job No.
- B26LA01701
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- epLan: Addition to and conversion of (e) detached garage into an ADU per LAMC 12.22 A.33(b)(1)
- Permit Issued
- Issued on 5/4/2026
- Issuing Office
- Current Status
- Issued on 5/4/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/21/2026 | APPLICANT |
| Assigned to Plan Check Engineer | 1/26/2026 | HOOMAN HAJIZADEH |
| Corrections Issued | 1/27/2026 | HOOMAN HAJIZADEH |
| Applicant returned to address corrections | 2/10/2026 | HOOMAN HAJIZADEH |
| Applicant returned to address corrections | 3/6/2026 | JOHNPAUL ISIP |
| Plan Check Approved | 4/11/2026 | JOHNPAUL ISIP |
| Issued | 5/4/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 2/3/2026 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 2/3/2026 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 2/4/2026 | MICHAEL BROWN |
| Sewer availability | Cleared | 2/4/2026 | MICHAEL BROWN |
| Construction near power lines | Cleared | 4/3/2026 | NAOMI GARCIA |
| Tenant Habitability Plan | Cleared | 4/8/2026 | HUGO GARRIDO GARZA |
Contact Information
| Contractor | Next Level Home Improvements; Lic. No.: 1120800-B | , |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/6/2026 | Conditional Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 5/6/2026 | Approved | SABAS ALONSO |
| Underground Mechanical | 5/6/2026 | Corrections Issued | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2026 | Corrections Issued | BRENDAN MORELLI |
| ELECTRICAL-Rough | 6/11/2026 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 6/22/2026 | Conditional Approval | SABAS ALONSO |
| Green Building Rough | 6/22/2026 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 6/22/2026 | Partial Approval | SABAS ALONSO |
| Insulation | 6/25/2026 | Approved | ALEX COLIN |
| BUILDING-Rough-Frame | 7/1/2026 | Approved | SABAS ALONSO |
| Drywall Nailing | 7/1/2026 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 7/14/2026 | Approved | SABAS ALONSO |
| Sewer | 7/14/2026 | Approved | SABAS ALONSO |
| Shower Pan | 7/14/2026 | Approved | SABAS ALONSO |
| Underground Mechanical | 7/14/2026 | Approved | SABAS ALONSO |