953 S GRAMERCY DR 90019
Certificate Information: 953 S GRAMERCY DR 90019
- Application / Permit
- 26014-10000-00141
- Plan Check / Job No.
- B26LA01305
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO REAR OF (E)SFD
- Permit Issued
- Issued on 2/18/2026
- Issuing Office
- Current Status
- CofO Issued on 6/4/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/15/2026 | APPLICANT |
| Assigned to Plan Check Engineer | 1/21/2026 | CARLOS MONTES |
| Corrections Issued | 1/22/2026 | CARLOS MONTES |
| Plan Check Approved | 2/1/2026 | CARLOS MONTES |
| Issued | 2/18/2026 | APPLICANT |
| CofO in Progress | 6/3/2026 | WILLIAM SIERRA |
| Permit Finaled | 6/4/2026 | DEROLD HAUFF |
| CofO Issued | 6/4/2026 | DEROLD HAUFF |
| Permit Finaled | 6/4/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/29/2026 | ROSE STEIN-WENDT |
| Roof/Waste drainage to street | Cleared | 1/29/2026 | ROSE STEIN-WENDT |
| Sewer availability | Cleared | 1/29/2026 | ROSE STEIN-WENDT |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 845 S. WILTON PL LOS ANGELES, CA 90005 |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/20/2026 | Corrections Issued | WILLIAM SIERRA |
| Footing/Foundation/Slab | 2/24/2026 | Approved | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2026 | Partial Approval | WILLIAM SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2026 | Partial Approval | WILLIAM SIERRA |
| ELECTRICAL-Rough | 3/18/2026 | Approved | WILLIAM SIERRA |
| HVAC-Rough | 3/18/2026 | Approved | WILLIAM SIERRA |
| PLUMBING-Rough | 3/18/2026 | Approved | WILLIAM SIERRA |
| BUILDING-Rough-Frame | 4/7/2026 | Approved | WILLIAM SIERRA |
| Green Building Rough | 4/7/2026 | Approved | WILLIAM SIERRA |
| Interior/Exterior Lathing | 4/7/2026 | Partial Approval | WILLIAM SIERRA |
| Insulation | 4/10/2026 | Approved | WILLIAM SIERRA |
| Drywall Nailing | 4/14/2026 | Approved | JUSTIN HAWLEY |
| Final | 5/22/2026 | Corrections Issued | WILLIAM SIERRA |
| Green Building Final | 5/22/2026 | Not Ready for Inspection | WILLIAM SIERRA |
| SGSOV-Seismic Gas S/O Valve | 5/22/2026 | SGSOV Approved | WILLIAM SIERRA |
| Smoke Detectors | 5/22/2026 | Approved | WILLIAM SIERRA |
| Final | 6/2/2026 | OK to Issue CofO | WILLIAM SIERRA |
| Green Building Final | 6/2/2026 | Approved | WILLIAM SIERRA |