3423-3425 W 60TH ST 90043

Certificate Information: 3423-3425 W 60TH ST 90043

Application / Permit
26014-10000-00108
Plan Check / Job No.
B26LA00811
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ADU ATTACHED TO THE REAR OF EXISTING SFD per GC 66323(a)(1) and per engineering
Permit Issued
Issued on 3/31/2026
Issuing Office
Metro
Current Status
Issued on 3/31/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/12/2026 APPLICANT
Assigned to Plan Check Engineer 1/15/2026 LUKE GONZALES
Corrections Issued 1/16/2026 LUKE GONZALES
Building Plans Picked Up 1/26/2026 APPLICANT
Applicant returned to address corrections 3/16/2026 EDWIN MARTINEZ
Plan Check Approved 3/27/2026 JOSE VELAZQUEZ
Issued 3/31/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/20/2026 JESUS CISNEROS
Roof/Waste drainage to street Cleared 3/20/2026 JESUS CISNEROS
Sewer availability Cleared 3/20/2026 JESUS CISNEROS
Eng Process Fee Ord 176,300 Cleared 3/24/2026 JESUS CISNEROS

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/13/2026 Corrections Issued JUSTIN HAWLEY
Deputy Drilled-In Anchors 5/15/2026 Conditional Approval RAUL BARAJAS
Footing/Foundation/Slab 5/18/2026 Corrections Issued SALVADOR MARTINEZ
Footing/Foundation/Slab 5/21/2026 Approved SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 6/17/2026 Partial Approval SABAS ALONSO
Sewer 6/17/2026 Approved SABAS ALONSO
Underground Mechanical 6/17/2026 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 6/24/2026 Partial Approval ALIZAH MAYAGOITIA
Insulation 6/24/2026 Partial Approval ALIZAH MAYAGOITIA