649-649 1/2 E 50TH ST 90011

Certificate Information: 649-649 1/2 E 50TH ST 90011

Application / Permit
26010-20000-01189
Plan Check / Job No.
B26VN06994
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW IRR SHAPED 40' x 41'-10" TWO-STORY DET 2 ACCESSORY DWELLING UNITS
Permit Issued
Issued on 5/29/2026
Issuing Office
Current Status
Issued on 5/29/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/17/2026 APPLICANT
Assigned to Plan Check Engineer 3/19/2026 SEAN SHAHMIRI
Assigned to Zoning Architect 3/19/2026 SAAD LADHANI
Corrections Issued 3/24/2026 SEAN SHAHMIRI
Quality Review Completed 3/25/2026 STEVEN KIM
Plan Check Approved 5/29/2026 SEAN SHAHMIRI
Issued 5/29/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 4/3/2026 JEFF LOREDO
Roof/Waste drainage to street Cleared 4/3/2026 JEFF LOREDO
Eng Process Fee Ord 176,300 Cleared 4/13/2026 JEFF LOREDO
Sewer availability Cleared 4/13/2026 JEFF LOREDO
Zoning Plan Check Cleared 4/22/2026 SAAD LADHANI

Contact Information

Contractor Owner-Builder       ,
Engineer Madero,, Fidencio; Lic. No.: C81695 PO BOX 40237      DOWNEY, CA 90239

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/15/2026 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 6/15/2026 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 6/15/2026 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 6/17/2026 Partial Approval BRENDAN MORELLI
PLUMBING-Rough 6/17/2026 Partial Approval BRENDAN MORELLI
Excavation/Setback/Form/Re-Bar 6/23/2026 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 7/8/2026 Partial Approval ALEJANDRO DE ARTOLA