8106 N JUMILLA AVE 91306
Certificate Information: 8106 N JUMILLA AVE 91306
- Application / Permit
- 26010-20000-00638
- Plan Check / Job No.
- B26VN04009
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT PER GCS 66323(A)(2)
- Permit Issued
- Issued on 3/11/2026
- Issuing Office
- Valley
- Current Status
- Issued on 3/11/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/13/2026 | APPLICANT |
| Assigned to Plan Check Engineer | 2/19/2026 | JEROME MAGAT PALMA |
| Corrections Issued | 2/21/2026 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 2/24/2026 | APPLICANT |
| Plan Check Approved | 3/9/2026 | YAQUB MIRZA |
| Issued | 3/11/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/6/2026 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 3/6/2026 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 3/6/2026 | WALLIE JONG |
| Sewer availability | Cleared | 3/6/2026 | WALLIE JONG |
Contact Information
| Contractor | Lee Enterprises And Management Corporation; Lic. No.: 1138286-B | 2475 KIMBERLY AVENUE CAMARILLO, CA 93010 |
| Engineer | Mroczka,, Peter J; Lic. No.: C42648 | 9301 DARBY AVE APT 1 NORTHRIDGE, CA 91325 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Final | 7/24/2026 |
| Service/Power Release | 7/24/2026 |
| Smoke Detectors | 7/24/2026 |
| SGSOV-Seismic Gas S/O Valve | 7/24/2026 |
| Green Building Final | 7/24/2026 |
Inspection Request History
| Pre-Inspection | 4/1/2026 | Partial Inspection | ALEXANDER HANDY |
| PLUMBING-Rough | 4/2/2026 | Partial Approval | ALEXANDER HANDY |
| Sewer | 4/2/2026 | Approved | ALEXANDER HANDY |
| Footing/Foundation/Slab | 4/8/2026 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 4/27/2026 | Partial Approval | ALEXANDER HANDY |
| ELECTRICAL-Rough | 4/27/2026 | Not Ready for Inspection | ALEXANDER HANDY |
| Green Building Rough | 4/27/2026 | Not Ready for Inspection | ALEXANDER HANDY |
| PLUMBING-Rough | 4/27/2026 | Approved | ALEXANDER HANDY |
| Verify Sprinkler Sign Off | 4/27/2026 | Not Ready for Inspection | ALEXANDER HANDY |
| ELECTRICAL-Rough | 4/28/2026 | Approved | JEFFREY HARTLINE |
| HVAC-Rough | 4/28/2026 | Not Ready for Inspection | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 4/30/2026 | Approved | ALEXANDER HANDY |
| Green Building Rough | 4/30/2026 | Approved | ALEXANDER HANDY |
| HVAC-Rough | 4/30/2026 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 4/30/2026 | Partial Approval | ALEXANDER HANDY |
| Verify Sprinkler Sign Off | 4/30/2026 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 5/6/2026 | Partial Approval | ALEXANDER HANDY |
| Insulation | 5/6/2026 | Corrections Issued | ALEXANDER HANDY |
| Drywall Nailing | 5/8/2026 | Approved | ARUTYUN MADATYAN |
| Insulation | 5/8/2026 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 5/22/2026 | Partial Approval | GEVORK IPCHYAN |
| Shower Pan | 5/22/2026 | Approved | GEVORK IPCHYAN |