8408 N BARDWELL AVE 91402
Certificate Information: 8408 N BARDWELL AVE 91402
- Application / Permit
- 26010-20000-00419
- Plan Check / Job No.
- B26VN02526
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: (N) DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1). WORK PER WFPP. 1 OF 2
- Permit Issued
- Issued on 2/26/2026
- Issuing Office
- Current Status
- Issued on 2/26/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/29/2026 | APPLICANT |
| Assigned to Plan Check Engineer | 2/2/2026 | OMAR GARNICA |
| Corrections Issued | 2/3/2026 | OMAR GARNICA |
| Applicant returned to address corrections | 2/19/2026 | ARAMIK SHAHMIRZAIAN |
| Applicant returned to address corrections | 2/24/2026 | ARAMIK SHAHMIRZAIAN |
| Plan Check Approved | 2/25/2026 | ARAMIK SHAHMIRZAIAN |
| Issued | 2/26/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 2/13/2026 | DERRICK MAGEE |
| Eng Process Fee Ord 176,300 | Cleared | 2/13/2026 | DERRICK MAGEE |
| Sewer availability | Cleared | 2/13/2026 | DERRICK MAGEE |
| Roof/Waste drainage to street | Cleared | 2/18/2026 | TONY CHIANG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/4/2026 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 3/23/2026 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 3/23/2026 | Corrections Issued | OGANES TARAKHCHYAN |
| Sewer | 3/23/2026 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 3/31/2026 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 4/3/2026 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2026 | Corrections Issued | DAVID ANDERSON |
| Green Building Rough | 4/24/2026 | Not Ready for Inspection | DAVID ANDERSON |
| Pre-Inspection | 4/24/2026 | Approved | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 4/24/2026 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 5/14/2026 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 5/14/2026 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 5/14/2026 | Corrections Issued | OGANES TARAKHCHYAN |
| Insulation | 5/27/2026 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 5/27/2026 | Partial Approval | OGANES TARAKHCHYAN |
| Drywall Nailing | 6/5/2026 | Approved | DAVID ANDERSON |