11124 N YOLANDA AVE 91326
Certificate Information: 11124 N YOLANDA AVE 91326
- Application / Permit
- 26010-20000-00213
- Plan Check / Job No.
- B26VN01065
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT PER GCS 66323(a)(2).
- Permit Issued
- Issued on 2/24/2026
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/27/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/14/2026 | APPLICANT |
| Assigned to Plan Check Engineer | 1/17/2026 | ARTIN ZARUKIAN |
| Corrections Issued | 1/17/2026 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 1/20/2026 | APPLICANT |
| Plan Check Approved | 2/24/2026 | YAQUB MIRZA |
| Issued | 2/24/2026 | APPLICANT |
| CofO in Progress | 5/20/2026 | JACK KARGODORIAN |
| Permit Finaled | 5/27/2026 | JOHN JANSON |
| CofO Issued | 5/27/2026 | JOHN JANSON |
| Permit Finaled | 5/27/2026 | JOHN JANSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/26/2026 | ALEXANDER HELFER |
| Address approval | Cleared | 1/29/2026 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 1/29/2026 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 1/29/2026 | MICHAEL BROWN |
| Sewer availability | Cleared | 1/29/2026 | MICHAEL BROWN |
| Construction near power lines | Cleared | 2/23/2026 | GEVORK KARAPETYAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/2/2026 | Partial Approval | DAVID SCANTLIN |
| Excavation/Setback/Form/Re-Bar | 3/4/2026 | Approved | DAVID SCANTLIN |
| Footing/Foundation/Slab | 3/4/2026 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 3/17/2026 | Not Ready for Inspection | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2026 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 3/17/2026 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 3/17/2026 | Not Ready for Inspection | DAVID SCANTLIN |
| PLUMBING-Rough | 3/17/2026 | Approved | DAVID SCANTLIN |
| Shower Pan | 3/17/2026 | Approved | DAVID SCANTLIN |
| Insulation | 3/20/2026 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 3/25/2026 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 3/25/2026 | Approved | DAVID SCANTLIN |
| Green Building Rough | 3/25/2026 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 3/25/2026 | Approved | DAVID SCANTLIN |
| MERV13>=Rough | 3/25/2026 | Approved | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 3/25/2026 | Approved | DAVID SCANTLIN |
| Final | 5/5/2026 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 5/5/2026 | Not Ready for Inspection | DAVID SCANTLIN |
| MERV13>=Final | 5/5/2026 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 5/5/2026 | SGSOV Approved | DAVID SCANTLIN |
| Service/Power Release | 5/5/2026 | Not Ready for Inspection | DAVID SCANTLIN |
| Smoke Detectors | 5/5/2026 | Approved | DAVID SCANTLIN |
| Final | 5/12/2026 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 5/12/2026 | Approved | JACK KARGODORIAN |
| Service/Power Release | 5/12/2026 | Not Ready for Inspection | JACK KARGODORIAN |
| Special/Order Compliance | 5/13/2026 | Partial Inspection | JACK KARGODORIAN |
| Final | 5/18/2026 | Corrections Issued | JACK KARGODORIAN |
| Service/Power Release | 5/18/2026 | Approved | JACK KARGODORIAN |
| Special/Order Compliance | 5/18/2026 | Partial Approval | JACK KARGODORIAN |
| Final | 5/19/2026 | OK to Issue CofO | JACK KARGODORIAN |
| Gas Test | 5/19/2026 | Approved | JACK KARGODORIAN |