8928 1/2 N HASKELL AVE 91343
Certificate Information: 8928 1/2 N HASKELL AVE 91343
- Application / Permit
- 26010-20000-00174
- Plan Check / Job No.
- B25VN33420
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT PER GC66323(a)(2) - ALL WORK PER WFPP *NFPA-13D FIRE SPRINKLERED THROUGHOUT
- Permit Issued
- Issued on 5/22/2026
- Issuing Office
- Current Status
- Issued on 5/22/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/12/2025 | APPLICANT |
| Assigned to Zoning Architect | 12/19/2025 | TRIAKSHA KALRA |
| Assigned to Plan Check Engineer | 1/8/2026 | DANIEL ABRAMYAN |
| Corrections Issued | 1/12/2026 | DANIEL ABRAMYAN |
| Quality Review Completed | 1/26/2026 | DAWN MC NULTY |
| Applicant returned to address corrections | 5/1/2026 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 5/18/2026 | DANIEL ABRAMYAN |
| Plan Check Approved | 5/22/2026 | DANIEL ABRAMYAN |
| Issued | 5/22/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 2/23/2026 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2026 | CARLOS AGUILERA |
| Sewer availability | Cleared | 2/25/2026 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 4/16/2026 | PATRICK PEREZ |
| Roof/Waste drainage to street | Cleared | 4/17/2026 | CELINA MORENO |
| Senate Bill 9 | Cleared | 5/11/2026 | TRIAKSHA KALRA |
| Zoning Plan Check | Cleared | 5/11/2026 | DANIEL ABRAMYAN |
Contact Information
| Contractor | Silva Design Construction Inc; Lic. No.: 956083-B | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/27/2026 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 5/27/2026 | Corrections Issued | JOSE AVILA |
| Deputy Reinf. Concrete | 5/28/2026 | Conditional Approval | JOSE AVILA |
| Footing/Foundation/Slab | 5/29/2026 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 5/29/2026 | Partial Approval | RAUL OLAGI |