1440 W 222ND ST 90501
Certificate Information: 1440 W 222ND ST 90501
- Application / Permit
- 26010-10000-01046
- Plan Check / Job No.
- B26LA08968
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN. (N) DETACHED ADU. PER LAMC 12.22 A.33(b)(1)
- Permit Issued
- Issued on 5/20/2026
- Issuing Office
- Current Status
- Issued on 5/20/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/9/2026 | APPLICANT |
| Assigned to Plan Check Engineer | 3/12/2026 | ALFREDO JARA |
| Corrections Issued | 3/13/2026 | ALFREDO JARA |
| Applicant returned to address corrections | 4/28/2026 | ALFREDO JARA |
| Plan Check Approved | 5/19/2026 | ALFREDO JARA |
| Issued | 5/20/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/2/2026 | STEPHANIE BOTROS |
| Eng Process Fee Ord 176,300 | Cleared | 4/14/2026 | STEPHANIE BOTROS |
| Sewer availability | Cleared | 4/14/2026 | STEPHANIE BOTROS |
| Roof/Waste drainage to street | Cleared | 5/16/2026 | DAVID LOPEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Tuna,, Suleyman; Lic. No.: C73294 | 1044 S MANSFIELD AVE. LOS ANGELES, CA 90019 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Wood Frame | 7/23/2026 |
Inspection Request History
| Pre-Inspection | 5/22/2026 | Corrections Issued | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 6/22/2026 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 6/25/2026 | Approved | EUGENE CASSIDY |
| METHANE-Barrier | 6/25/2026 | Approved | EUGENE CASSIDY |
| METHANE-Subgrade | 6/25/2026 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 7/6/2026 | Partial Approval | EUGENE CASSIDY |
| Green Building Rough | 7/6/2026 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Rough | 7/6/2026 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 7/6/2026 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 7/9/2026 | Approved | ARTHUR NEGRETE |
| Green Building Rough | 7/9/2026 | Not Ready for Inspection | ARTHUR NEGRETE |
| METHANE-Rough | 7/9/2026 | Approved | ARTHUR NEGRETE |
| Verify Sprinkler Sign Off | 7/9/2026 | Not Ready for Inspection | ARTHUR NEGRETE |