1333 1/2-3/4 W CARSON ST 90501
Certificate Information: 1333 1/2-3/4 W CARSON ST 90501
- Application / Permit
- 26010-10000-00864
- Plan Check / Job No.
- B26LA01797
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY, 2 UNIT ADU
- Permit Issued
- Issued on 4/14/2026
- Issuing Office
- Current Status
- Issued on 4/14/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/22/2026 | APPLICANT |
| Assigned to Plan Check Engineer | 2/12/2026 | JOE VO |
| Assigned to Zoning Architect | 2/19/2026 | KRISTEL MARQUEZ |
| Corrections Issued | 2/23/2026 | JOE VO |
| Quality Review Completed | 3/2/2026 | GARO TELMI |
| Plan Check Approved | 4/2/2026 | JOE VO |
| Issued | 4/14/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/10/2026 | JESUS CISNEROS |
| Low Impact Development (LID) | Cleared | 3/10/2026 | MARCO SANCHEZ |
| DAS Clearance | Cleared | 3/12/2026 | JOE VO |
| Hydrant and Access approval | Cleared | 3/12/2026 | KURT CORRAL |
| Roof/Waste drainage to street | Cleared | 3/12/2026 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 3/16/2026 | STEVE MELGAR |
| Sewer availability | Cleared | 3/16/2026 | STEVE MELGAR |
| Green Code | Cleared | 3/18/2026 | AARON COSTA |
| Zoning Plan Check | Cleared | 3/24/2026 | KRISTEL MARQUEZ |
Contact Information
| Contractor | Adu Express Construction Llc; Lic. No.: 1035634-B | , |
| Contractor | Arash Mofakham; Lic. No.: 1035634-B | , |
| Engineer | Aalam,, Yahya; Lic. No.: C94318 | 3111 4TH ST APT 401 SANTA MONICA, CA 90405 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/20/2026 | Corrections Issued | BEN MOLSTAD |
| Underground Mechanical | 5/22/2026 | Partial Approval | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 6/2/2026 | Corrections Issued | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 6/25/2026 | Partial Approval | EUGENE CASSIDY |