10818 1/2 S WILLOWBROOK AVE 90059

Certificate Information: 10818 1/2 S WILLOWBROOK AVE 90059

Application / Permit
26010-10000-00316
Plan Check / Job No.
B26LA02047
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan NEW DETACHED 2-STORY ADU 1,200 SF PER LAMC 12.22 A.33(b)(1)
Permit Issued
Issued on 3/19/2026
Issuing Office
Current Status
Issued on 3/19/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/21/2026 APPLICANT
Assigned to Plan Check Engineer 1/29/2026 JOSEPH RAFOLS
Assigned to Zoning Architect 1/29/2026 MANUEL ZAVALETA
Corrections Issued 2/3/2026 JOSEPH RAFOLS
Quality Review Completed 2/19/2026 SINA KHOSRAVI
Plan Check Approved 3/18/2026 JOSEPH RAFOLS
Issued 3/19/2026 APPLICANT

Permit Application Clearance Information

Hydrant and Access approval Cleared 2/27/2026 LAVEON RIDER
Low Impact Development (LID) Cleared 2/27/2026 MARTIN FRAGOSO
Address approval Cleared 3/5/2026 TONY CHIANG
Roof/Waste drainage to street Cleared 3/5/2026 TONY CHIANG
Zoning Plan Check Cleared 3/6/2026 Rosendo Medina
Eng Process Fee Ord 176,300 Cleared 3/9/2026 TONY CHIANG
Metro Rail approval Cleared 3/10/2026 JENNIFER SU
Sewer availability Cleared 3/16/2026 TONY CHIANG

Contact Information

Contractor Ebenezer Construction; Lic. No.: 657529-B       ,
Engineer Sandoval,, Martin; Lic. No.: C56905 12761 DAIRY ST      EASTVALE, CA 92880

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/25/2026 Approved ARTHUR NEGRETE
PLUMBING-Rough 3/25/2026 Approved ARTHUR NEGRETE
Underground Mechanical 3/25/2026 Approved ARTHUR NEGRETE
Footing/Foundation/Slab 5/7/2026 Approved ARTHUR NEGRETE
PLUMBING-Rough 5/7/2026 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 6/1/2026 Not Ready for Inspection ARTHUR NEGRETE
Floor/Roof Diaphrgm/Shear Wall 6/1/2026 Approved ARTHUR NEGRETE
Green Building Rough 6/1/2026 Not Ready for Inspection ARTHUR NEGRETE
Verify Sprinkler Sign Off 6/1/2026 Not Ready for Inspection ARTHUR NEGRETE
Wood Frame 6/1/2026 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 6/24/2026 Not Ready for Inspection ARTHUR NEGRETE
Floor/Roof Diaphrgm/Shear Wall 6/24/2026 Approved ARTHUR NEGRETE
Green Building Rough 6/24/2026 Not Ready for Inspection ARTHUR NEGRETE
Verify Sprinkler Sign Off 6/24/2026 Not Ready for Inspection ARTHUR NEGRETE