7048 N BERTRAND AVE 91335
Certificate Information: 7048 N BERTRAND AVE 91335
- Application / Permit
- 26010-10000-00083
- Plan Check / Job No.
- B26LA00280
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan: Proposed 1 story single family dueling unit per SB9 Development.
- Permit Issued
- Issued on 6/23/2026
- Issuing Office
- Current Status
- Issued on 6/23/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/6/2026 | APPLICANT |
| Assigned to Plan Check Engineer | 1/29/2026 | RACHEL BEYENE |
| Assigned to Zoning Architect | 1/30/2026 | LINGHUI YU |
| Corrections Issued | 2/9/2026 | RACHEL BEYENE |
| Quality Review Completed | 2/17/2026 | GARO TELMI |
| Applicant returned to address corrections | 3/2/2026 | RACHEL BEYENE |
| Applicant returned to address corrections | 3/18/2026 | RACHEL BEYENE |
| Applicant returned to address corrections | 6/18/2026 | RACHEL BEYENE |
| Plan Check Approved | 6/22/2026 | RACHEL BEYENE |
| Issued | 6/23/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/3/2026 | ROSE STEIN-WENDT |
| Roof/Waste drainage to street | Cleared | 4/3/2026 | ROSE STEIN-WENDT |
| Eng Process Fee Ord 176,300 | Cleared | 4/6/2026 | ROSE STEIN-WENDT |
| Hydrant and Access approval | Cleared | 4/6/2026 | JOHN CONNEALLY |
| Sewer availability | Cleared | 4/6/2026 | ROSE STEIN-WENDT |
| Senate Bill 9 | Cleared | 4/7/2026 | MAYELA VILLA |
| Construction near power lines | Cleared | 5/6/2026 | GEVORK KARAPETYAN |
| Zoning Plan Check | Cleared | 5/18/2026 | LINGHUI YU |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zolfaghari,, Saeed; Lic. No.: C86761 | 6201 BEE AVE AGOURA HILLS, CA 91301 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/26/2026 | Partial Approval | ARUTYUN MADATYAN |
| Sewer | 6/26/2026 | Approved | ARUTYUN MADATYAN |
| Underground Mechanical | 6/26/2026 | Partial Approval | ARUTYUN MADATYAN |
| Excavation/Setback/Form/Re-Bar | 7/7/2026 | Approved | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 7/7/2026 | Approved | ARUTYUN MADATYAN |
| Excavation/Setback/Form/Re-Bar | 7/9/2026 | Approved | ARUTYUN MADATYAN |
| Excavation/Setback/Form/Re-Bar | 7/13/2026 | Approved | ARUTYUN MADATYAN |