5660 N COLUMBUS AVE 91411
Certificate Information: 5660 N COLUMBUS AVE 91411
- Application / Permit
- 26010-10000-00063
- Plan Check / Job No.
- B26LA00248
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- [ePlan] NEW 2-STORY ADU PER LAMC 12.22 A.33(b)(1)
- Permit Issued
- Issued on 4/3/2026
- Issuing Office
- Current Status
- Issued on 4/3/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/7/2026 | APPLICANT |
| Assigned to Zoning Architect | 1/9/2026 | RYAN DEL POSO |
| Assigned to Plan Check Engineer | 1/15/2026 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 1/20/2026 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 1/28/2026 | GARO TELMI |
| Applicant returned to address corrections | 4/1/2026 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 4/3/2026 | MAHNAZ NOURHASHEMI |
| Issued | 4/3/2026 | APPLICANT |
Permit Application Clearance Information
| Miscellaneous | Cleared | 2/11/2026 | ROSALINDA MEZA |
| ZI | Cleared | 2/11/2026 | ROSALINDA MEZA |
| Address approval | Cleared | 2/28/2026 | JOHN LIN |
| Roof/Waste drainage to street | Cleared | 2/28/2026 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 3/9/2026 | JOHN LIN |
| Sewer availability | Cleared | 3/9/2026 | JOHN LIN |
| Construction near power lines | Cleared | 3/11/2026 | GEVORK KARAPETYAN |
| Construction within easement | Cleared | 3/11/2026 | GEVORK KARAPETYAN |
| Zoning Plan Check | Cleared | 3/12/2026 | RYAN DEL POSO |
Contact Information
| Contractor | Shaolian Sol K And Assoc Inc; Lic. No.: 720390-B | , |
| Contractor | Sks Construction; Lic. No.: 720390-B | , |
| Engineer | Shaolian,, Shahab Joseph; Lic. No.: C84155 | 15134 FRIAR ST VAN NUYS, CA 91411 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/8/2026 | Partial Approval | VINCENT HANLEY |
| Sewer | 4/8/2026 | Approved | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 4/15/2026 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 4/15/2026 | Approved | VINCENT HANLEY |
| Underground Mechanical | 4/28/2026 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2026 | Corrections Issued | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2026 | Partial Approval | VINCENT HANLEY |
| Underground Mechanical | 5/11/2026 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2026 | Partial Approval | VINCENT HANLEY |
| Deputy Wood Construction | 6/4/2026 | Conditional Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2026 | Approved | VINCENT HANLEY |