726 S HOLMBY AVE 90024

Certificate Information: 726 S HOLMBY AVE 90024

Application / Permit
25047-30000-00216
Plan Check / Job No.
B25WL01318
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
New Swimming Pool w/ Spa per standard plan 265. --- 1 of 3--
Permit Issued
Issued on 5/14/2025
Issuing Office
West Los Angeles
Current Status
CofO Issued on 2/17/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/21/2025 APPLICANT
Assigned to Plan Check Engineer 2/27/2025 EDWIN ESPIN
Corrections Issued 3/7/2025 EDWIN ESPIN
Quality Review Completed 3/13/2025 CHIHARU SUZUKI
Building Plans Picked Up 3/17/2025 APPLICANT
Applicant returned to address corrections 5/2/2025 EDWIN ESPIN
Plan Check Approved 5/14/2025 EDWIN ESPIN
Issued 5/14/2025 APPLICANT
CofO in Progress 2/13/2026 RYAN SALAZAR
Permit Finaled 2/17/2026 RICHARD STEINBACH
CofO Issued 2/17/2026 RICHARD STEINBACH
Permit Finaled 2/17/2026 RICHARD STEINBACH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/3/2025 EDWIN ESPIN
Eng Process Fee Ord 176,300 Cleared 3/4/2025 DARIN LAM
Miscellaneous Cleared 4/10/2025 DIANA RENTERIA

Contact Information

Contractor Eurocon Group Inc; Lic. No.: 708010-B 923 HILTS AVE      LOS ANGELES, CA 90024
Engineer Mahn,, Jonathan Edward; Lic. No.: C60293 12848 FOOTHILL BLVD      SYLMAR, CA 91381
Engineer Zhang,, Yao; Lic. No.: C74572 538 ROCCO CIRCLE      CORONA, CA 92882
Geologist Triebold,, Mark John; Lic. No.: EG1796 6906 QUITO COURT      CAMARILLO, CA 93012

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/23/2025 Corrections Issued DANIEL VERA
Grounding or Bonding 6/23/2025 Approved DANIEL VERA
Rough-Plumbing 6/23/2025 Not Ready for Inspection DANIEL VERA
Green Building Rough 6/26/2025 Not Ready for Inspection DANIEL VERA
Pre-Gunite 6/26/2025 Not Ready for Inspection DANIEL VERA
Rough-Electrical 6/26/2025 Not Ready for Inspection DANIEL VERA
Rough-Plumbing 6/26/2025 Not Ready for Inspection DANIEL VERA
Green Building Rough 6/30/2025 Approved DANIEL VERA
Pre-Gunite 6/30/2025 Approved DANIEL VERA
Rough-Electrical 6/30/2025 Approved DANIEL VERA
Rough-Plumbing 6/30/2025 Approved DANIEL VERA
Grounding or Bonding 9/2/2025 Approved DANIEL VERA
Enclosure/Fence 12/3/2025 Corrections Issued DANIEL VERA
PLUMBING-Final 12/3/2025 Not Ready for Inspection DANIEL VERA
Excavation/Setback/Form/Re-Bar 12/15/2025 Approved DANIEL VERA
Final 12/15/2025 Not Ready for Inspection DANIEL VERA
Green Building Final 12/15/2025 Approved DANIEL VERA
SGSOV-Seismic Gas S/O Valve 12/15/2025 SGSOV Not Ready DANIEL VERA
Final 1/26/2026 Corrections Issued CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 1/26/2026 SGSOV Approved CARLOS MATAMOROS
Final 2/2/2026 Conditional Approval EVAN COOPER
Deputy Shotcrete 2/13/2026 Conditional Approval RYAN SALAZAR
Final 2/13/2026 OK to Issue CofO RYAN SALAZAR