4337 W 59TH ST 90043

Certificate Information: 4337 W 59TH ST 90043

Application / Permit
25047-20000-01428
Plan Check / Job No.
B25VN31354
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
New swimming pool per standard plan and Engineer details
Permit Issued
Issued on 12/23/2025
Issuing Office
Valley
Current Status
Issued on 12/23/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/24/2025 APPLICANT
Assigned to Plan Check Engineer 10/24/2025 MOHAMMAD ESMAILI
Corrections Issued 10/24/2025 MOHAMMAD ESMAILI
Applicant returned to address corrections 11/19/2025 ALEC MOUSAKHANIAN
Plan Check Approved 12/23/2025 MINA HABILI
Issued 12/23/2025 APPLICANT

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Soto Pools Inc; Lic. No.: 1104149-C53 14173 ASTORIA STREET      SYLMAR, CA 91342
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/8/2026 Corrections Issued SALVADOR MARTINEZ
Gunite 2/4/2026 Corrections Issued SALVADOR MARTINEZ
Grounding or Bonding 2/10/2026 Partial Approval SALVADOR MARTINEZ
Pool Piping 2/10/2026 Corrections Issued SALVADOR MARTINEZ
Pre-Gunite 2/10/2026 Corrections Issued SALVADOR MARTINEZ
Pool Piping 2/12/2026 Approved SALVADOR MARTINEZ
Pre-Gunite 2/12/2026 Approved SALVADOR MARTINEZ
Deputy Other (see comments) 2/17/2026 Conditional Approval SALVADOR MARTINEZ
Deputy Shotcrete 2/17/2026 Conditional Approval SALVADOR MARTINEZ
Gunite 2/27/2026 Approved SALVADOR MARTINEZ
Rough-Electrical 2/27/2026 Corrections Issued SALVADOR MARTINEZ
Rough-Electrical 3/3/2026 Partial Approval SALVADOR MARTINEZ
Rough-Electrical 3/10/2026 Partial Approval SALVADOR MARTINEZ
Enclosure/Fence 4/2/2026 Corrections Issued SALVADOR MARTINEZ
Grounding or Bonding 4/2/2026 Corrections Issued SALVADOR MARTINEZ
Enclosure/Fence 4/15/2026 Corrections Issued SALVADOR MARTINEZ
Enclosure/Fence 4/17/2026 Corrections Issued SALVADOR MARTINEZ
Deck 4/21/2026 Not Ready for Inspection SALVADOR MARTINEZ
Grounding or Bonding 4/21/2026 Not Ready for Inspection SALVADOR MARTINEZ
Enclosure/Fence 5/1/2026 Conditional Approval SALVADOR MARTINEZ
Grounding or Bonding 5/1/2026 Corrections Issued SALVADOR MARTINEZ
Enclosure/Fence 5/5/2026 Approved SALVADOR MARTINEZ
Grounding or Bonding 5/5/2026 Approved SALVADOR MARTINEZ