23463 W SYLVAN ST 91367
Certificate Information: 23463 W SYLVAN ST 91367
- Application / Permit
- 25047-20000-01360
- Plan Check / Job No.
- B25VN30206
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 32'x17' POOL AND 8'x10' SPA PER LA CITY STANDARD PLAN# 268.
- Permit Issued
- Issued on 10/22/2025
- Issuing Office
- Current Status
- CofO in Progress on 5/14/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/14/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/14/2025 | JESSE ARELLANO |
| Corrections Issued | 10/14/2025 | JESSE ARELLANO |
| Plan Check Approved | 10/22/2025 | NAREG ATARIAN |
| Issued | 10/22/2025 | APPLICANT |
| CofO in Progress | 5/14/2026 | TROY SANDERS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 10/21/2025 | WALTER RAMIREZ |
| Construction within easement | Cleared | 10/22/2025 | WALTER RAMIREZ |
Contact Information
| Contractor | Adu Builder And Construction Inc; Lic. No.: 1122843-B | 5030 NEWCASTLE AVE ENCINO, CA 91316 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grounding or Bonding | 10/29/2025 | Not Ready for Inspection | TROY SANDERS |
| Excavation/Setback/Form/Re-Bar | 11/3/2025 | Approved | TROY SANDERS |
| Pre-Gunite | 11/3/2025 | Approved | TROY SANDERS |
| Rough-Plumbing | 11/3/2025 | Approved | TROY SANDERS |
| Deputy Shotcrete | 11/4/2025 | Conditional Approval | ROBERT GOLD |
| Gas Piping or Gas Test | 12/5/2025 | Approved | TROY SANDERS |
| Grounding or Bonding | 2/12/2026 | Approved | TROY SANDERS |
| Enclosure/Fence | 3/11/2026 | Approved | TROY SANDERS |
| Equipment Noise Level | 4/28/2026 | Approved | ALFREDO FLORES |
| Final | 5/12/2026 | OK to Issue CofO | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 5/12/2026 | SGSOV Approved | TROY SANDERS |