5115 E LONGFELLOW ST 90042

Certificate Information: 5115 E LONGFELLOW ST 90042

Application / Permit
25047-20000-01349
Plan Check / Job No.
B25VN29959
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW POOL PER LA CITY STANDARD PLAN # 268.
Permit Issued
Issued on 11/25/2025
Issuing Office
Valley
Current Status
Issued on 11/25/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/10/2025 APPLICANT
Assigned to Plan Check Engineer 10/10/2025 SARKIS HARABEDIAN
Corrections Issued 10/10/2025 SARKIS HARABEDIAN
Applicant returned to address corrections 10/21/2025 KAMYAR EMAMI
Plan Check Approved 11/25/2025 SAMUEL GONZALEZ
Issued 11/25/2025 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 10/10/2025 SARKIS HARABEDIAN
HPOZ Cleared 10/16/2025 FIPE LEILUA

Contact Information

Contractor Way To Go Builders; Lic. No.: 1043721-B 6700 FALLBROOK AVE #133      WEST HILLS, CA 91307
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/5/2026 Approved ALIZAH MAYAGOITIA
Rough-Plumbing 2/5/2026 Approved ALIZAH MAYAGOITIA
Deputy Shotcrete 2/9/2026 Conditional Approval LILIANA PORTILLO
Final 4/13/2026 Corrections Issued LILIANA PORTILLO
Pre-Gunite 4/13/2026 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 4/13/2026 SGSOV Not Ready LILIANA PORTILLO
Deck 4/23/2026 Corrections Issued LILIANA PORTILLO
Enclosure/Fence 4/23/2026 Corrections Issued LILIANA PORTILLO
Deck 4/27/2026 Not Ready for Inspection DAVID WILLIAMS
Enclosure/Fence 4/27/2026 Not Ready for Inspection DAVID WILLIAMS
Enclosure/Fence 5/20/2026 Approved LILIANA PORTILLO
Grounding or Bonding 5/20/2026 Approved LILIANA PORTILLO