11741 W LA MAIDA ST 91607
Certificate Information: 11741 W LA MAIDA ST 91607
- Application / Permit
- 25047-20000-01226
- Plan Check / Job No.
- B25VN27227
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 14' x 22' POOL AND 8' x 8' SPA PER LA CITY STANDARD PLAN #268.
- Permit Issued
- Issued on 9/26/2025
- Issuing Office
- Current Status
- CofO in Progress on 5/18/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/17/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/17/2025 | GIOVANNY CHAVEZ |
| Corrections Issued | 9/18/2025 | GIOVANNY CHAVEZ |
| Plan Check Approved | 9/26/2025 | GIOVANNY CHAVEZ |
| Issued | 9/26/2025 | APPLICANT |
| CofO in Progress | 5/18/2026 | JAVIER RAMOS JR |
Permit Application Clearance Information
| Construction near power lines | Cleared | 9/22/2025 | WALTER RAMIREZ |
| Miscellaneous | Cleared | 9/23/2025 | JACQUELINE TORRES |
Contact Information
| Contractor | Agam Pool And Spa Inc; Lic. No.: 993464-C53 | , |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 10/24/2025 | Approved | JAVIER RAMOS JR |
| Deputy Shotcrete | 10/28/2025 | Conditional Approval | JAVIER RAMOS JR |
| Grounding or Bonding | 3/6/2026 | Approved | JAVIER RAMOS JR |
| Enclosure/Fence | 4/28/2026 | Corrections Issued | JAVIER RAMOS JR |
| Enclosure/Fence | 5/4/2026 | Corrections Issued | JAVIER RAMOS JR |
| Enclosure/Fence | 5/5/2026 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 5/15/2026 | Approved | JAVIER RAMOS JR |
| Equipment Noise Level | 5/15/2026 | Approved | ALFREDO FLORES |
| Excavation/Setback/Form/Re-Bar | 5/15/2026 | Approved | JAVIER RAMOS JR |
| Final | 5/15/2026 | OK to Issue CofO | JAVIER RAMOS JR |
| Green Building Final | 5/15/2026 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 5/15/2026 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 5/15/2026 | SGSOV Approved | JAVIER RAMOS JR |