13853 W CHANDLER BLVD 91401

Certificate Information: 13853 W CHANDLER BLVD 91401

Application / Permit
25047-20000-01175
Plan Check / Job No.
B25VN22509
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW SWIMMING POOL AND SPA PER STANDARD PLAN # 268 AND ENGINEERING DETAILS
Permit Issued
Issued on 9/5/2025
Issuing Office
Current Status
CofO in Progress on 7/17/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/5/2025 APPLICANT
Assigned to Plan Check Engineer 8/7/2025 RARES BODEA
Corrections Issued 8/12/2025 RARES BODEA
Quality Review Completed 8/13/2025 STEVEN KIM
Building Plans Picked Up 8/14/2025 APPLICANT
Applicant returned to address corrections 9/5/2025 RARES BODEA
Plan Check Approved 9/5/2025 RARES BODEA
Issued 9/5/2025 APPLICANT
CofO in Progress 7/17/2026 VINCENT HANLEY

Permit Application Clearance Information

Construction near power lines Cleared 9/5/2025 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Amar,, David; Lic. No.: C97582 6160 CORBIN AVENUE      TARZANA, CA 91356
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/22/2025 Approved RYAN SALAZAR
Pool Piping 10/22/2025 Approved RYAN SALAZAR
Deputy Shotcrete 10/23/2025 Conditional Approval JOAQUIN GREENOUGH
Gas Piping or Gas Test 4/10/2026 Approved VINCENT HANLEY
Grounding or Bonding 4/10/2026 Corrections Issued VINCENT HANLEY
Gas Piping or Gas Test 4/13/2026 Approved VINCENT HANLEY
Grounding or Bonding 4/13/2026 Approved VINCENT HANLEY
Enclosure/Fence 6/15/2026 Approved VINCENT HANLEY
Enclosure/Fence 6/16/2026 Approved VINCENT HANLEY
Pool Equipment Noise Test 7/15/2026 Approved FELIPE PENICHE
Final 7/16/2026 OK to Issue CofO VINCENT HANLEY
Green Building Final 7/16/2026 Approved VINCENT HANLEY
Green Building Rough 7/16/2026 Approved VINCENT HANLEY
Pre-Gunite 7/16/2026 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 7/16/2026 SGSOV Approved VINCENT HANLEY