4906 N PLACIDIA AVE 91601
Certificate Information: 4906 N PLACIDIA AVE 91601
- Application / Permit
- 25047-20000-01162
- Plan Check / Job No.
- B25VN25705
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- PROPOSED NEW SWIMMING POOL W/ SPA PER CITY STD PLAN #268 & SUPPL ENGR DETAILS.
- Permit Issued
- Issued on 10/6/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/13/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/3/2025 | HAYATO TSUCHIYA |
| Corrections Issued | 9/3/2025 | HAYATO TSUCHIYA |
| Plan Check Approved | 10/6/2025 | ISIS ARGUETA |
| Issued | 10/6/2025 | APPLICANT |
| CofO in Progress | 2/25/2026 | ROBERTO PALACIOS-LOPEZ |
| Permit Finaled | 3/13/2026 | RUBEN SALAS |
| CofO Issued | 3/13/2026 | RUBEN SALAS |
| Permit Finaled | 3/13/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Construction within easement | Cleared | 10/1/2025 | GEVORK KARAPETYAN |
Contact Information
| Contractor | R S P P S Inc; Lic. No.: 998562-C53 | 24418 HAMPTON DRIVE UNIT B VALENCIA, CA 91355 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Piping or Gas Test | 10/27/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Pool Piping | 10/27/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Pre-Gunite | 10/27/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Deputy Shotcrete | 11/4/2025 | Conditional Approval | JUAN VALENZUELA |
| Gas Piping or Gas Test | 11/12/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 11/12/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Grounding or Bonding | 11/26/2025 | Approved | JAVIER RAMOS JR |
| Enclosure/Fence | 12/12/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Pre-Inspection | 12/12/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Enclosure/Fence | 12/30/2025 | Corrections Issued | JAVIER RAMOS JR |
| Enclosure/Fence | 2/5/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Excavation/Setback/Form/Re-Bar | 2/5/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 2/5/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Pool Equipment Noise Test | 2/5/2026 | Approved | FELIPE PENICHE |
| SGSOV-Seismic Gas S/O Valve | 2/5/2026 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| Enclosure/Fence | 2/24/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 2/24/2026 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 2/24/2026 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |