20361 W EDGEWOOD CT 91311

Certificate Information: 20361 W EDGEWOOD CT 91311

Application / Permit
25047-20000-01150
Plan Check / Job No.
B25VN25368
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW POOL AND SPA PER STANDARD PLAN #268 AND SUPPLEMENTAL ENGINEERING DETAILS.
Permit Issued
Issued on 10/21/2025
Issuing Office
Valley
Current Status
Issued on 10/21/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/29/2025 APPLICANT
Assigned to Plan Check Engineer 9/4/2025 ARAMIK SHAHMIRZAIAN
Corrections Issued 9/4/2025 ARAMIK SHAHMIRZAIAN
Building Plans Picked Up 9/5/2025 APPLICANT
Applicant returned to address corrections 10/16/2025 NAREG ATARIAN
Plan Check Approved 10/21/2025 GIOVANNY CHAVEZ
Issued 10/21/2025 APPLICANT

Permit Application Clearance Information

"T" removal Cleared 9/25/2025 ASHLEY RODARTE
CPC Cleared 9/25/2025 ASHLEY RODARTE
ZA Case Cleared 9/25/2025 ASHLEY RODARTE

Contact Information

Contractor Aquaterra Landscape Inc; Lic. No.: 1098622-C27 117 PARAKEET      IRVINE, CA 92620
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Rough-Mechanical 1/23/2026 Corrections Issued DAVID SCANTLIN
Green Building Rough 2/12/2026 Not Ready for Inspection DAVID SCANTLIN
Pre-Gunite 2/12/2026 Corrections Issued DAVID SCANTLIN
Pool Piping 2/14/2026 Approved KEVIN BERBERYAN
Pre-Gunite 2/14/2026 Partial Approval KEVIN BERBERYAN
Rough-Electrical 2/14/2026 Approved KEVIN BERBERYAN
Rough-Plumbing 2/14/2026 Approved KEVIN BERBERYAN
Deputy Shotcrete 2/17/2026 Conditional Approval HENRY KIM
Special/Order Compliance 2/19/2026 Corrections Issued DAVID SCANTLIN
Gas Piping or Gas Test 3/3/2026 Corrections Issued JACK KARGODORIAN
Rough-Electrical 3/3/2026 Not Ready for Inspection JACK KARGODORIAN
Deck 4/2/2026 Corrections Issued JACK KARGODORIAN
Grounding or Bonding 4/2/2026 Not Ready for Inspection JACK KARGODORIAN
Grounding or Bonding 4/8/2026 Approved JACK KARGODORIAN
Grounding or Bonding 6/11/2026 Approved JEFFREY PARD