17240 W CITRONIA ST 91325

Certificate Information: 17240 W CITRONIA ST 91325

Application / Permit
25047-20000-01139
Plan Check / Job No.
B25VN25223
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 48'-3" x 26'-10" SWIMMING POOL AND 10'-11" DIAMETER SPA PER LA CITY STANDARD PLAN #268.
Permit Issued
Issued on 9/17/2025
Issuing Office
Valley
Current Status
Issued on 3/10/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/28/2025 APPLICANT
Assigned to Plan Check Engineer 8/28/2025 GIOVANNY CHAVEZ
Corrections Issued 8/28/2025 GIOVANNY CHAVEZ
Plan Check Approved 9/17/2025 GIOVANNY CHAVEZ
Issued 9/17/2025 APPLICANT
Refund in Progress 1/6/2026 SELENIA GARCIA
Refund Closed 1/6/2026 SELENIA GARCIA
Issued 1/6/2026 SELENIA GARCIA
Refund in Progress 1/27/2026 SUZY TER-OGANESYAN
Refund Denied 3/10/2026 EMILY HU
Issued 3/10/2026 EMILY HU

Permit Application Clearance Information

Grading Pre-Inspection Cleared 9/17/2025 GIOVANNY CHAVEZ
ZA Case Cleared 9/17/2025 ROSALINDA MEZA
ZA Case Cleared 9/17/2025 ROSALINDA MEZA

Contact Information

Contractor Pacific Outdoor Living; Lic. No.: 715731-B 8309 TUJUNGA AVE SUITE 201      SUN VALLEY, CA 91352
Engineer Thompson,, Matthew Gregory; Lic. No.: C86051 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deck 1/26/2026 Approved ROBERTO PALACIOS-LOPEZ
Gas Piping or Gas Test 1/26/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Pool Piping 1/26/2026 Approved ROBERTO PALACIOS-LOPEZ
Pre-Gunite 1/26/2026 Partial Approval ROBERTO PALACIOS-LOPEZ
Rough-Electrical 1/26/2026 Partial Approval ROBERTO PALACIOS-LOPEZ
Enclosure/Fence 6/4/2026 Corrections Issued CHRISTOPHER ROJAS
Special/Order Compliance 6/4/2026 Corrections Issued CHRISTOPHER ROJAS
Enclosure/Fence 6/10/2026 Approved CHRISTOPHER ROJAS
Excavation/Setback/Form/Re-Bar 7/7/2026 Approved KEVIN BERBERYAN
Final 7/7/2026 Corrections Issued KEVIN BERBERYAN
Green Building Final 7/7/2026 Approved KEVIN BERBERYAN
Green Building Rough 7/7/2026 Approved KEVIN BERBERYAN
Pre-Gunite 7/7/2026 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 7/7/2026 SGSOV Approved KEVIN BERBERYAN