22122 W GERMAIN ST 91311

Certificate Information: 22122 W GERMAIN ST 91311

Application / Permit
25047-20000-01059
Plan Check / Job No.
B25VN23705
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW POOL AND SPA WITH BAJA PER LA CITY STANDARD PLAN #268.
Permit Issued
Issued on 8/20/2025
Issuing Office
Valley
Current Status
CofO Issued on 12/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/15/2025 APPLICANT
Assigned to Plan Check Engineer 8/15/2025 ARAMIK SHAHMIRZAIAN
Corrections Issued 8/15/2025 ARAMIK SHAHMIRZAIAN
Plan Check Approved 8/20/2025 SARKIS HARABEDIAN
Issued 8/20/2025 APPLICANT
CofO in Progress 12/10/2025 JEFFREY PARD
CofO in Progress 12/12/2025 JEFFREY PARD
CofO in Progress 12/15/2025 JEFFREY PARD
Permit Finaled 12/16/2025 JOHN JANSON
CofO Issued 12/16/2025 JOHN JANSON
Permit Finaled 12/16/2025 JOHN JANSON

Permit Application Clearance Information

Grading Pre-Inspection Cleared 8/20/2025 ARAMIK SHAHMIRZAIAN

Contact Information

Contractor Feldman Yosef; Lic. No.: 1118256-B 10905 OHIO AVE APT 125      LOS ANGELES, CA 90024
Engineer Thompson,, Matthew Gregory; Lic. No.: C86051 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/29/2025 Approved SCOTT SOBEL
Rough-Plumbing 9/29/2025 Partial Approval SCOTT SOBEL
Deputy Shotcrete 10/1/2025 Conditional Approval STEVEN BACK
Gas Piping or Gas Test 10/6/2025 Approved JEFFREY PARD
Rough-Electrical 10/6/2025 Approved JEFFREY PARD
Deck 10/29/2025 Approved GEVORK IPCHYAN
Enclosure/Fence 10/29/2025 Corrections Issued GEVORK IPCHYAN
Enclosure/Fence 11/12/2025 Corrections Issued HENRY KIM
Pool Equipment Noise Test 12/1/2025 Approved ALFREDO FLORES
Final 12/9/2025 Partial Approval JEFFREY PARD
Pre-Gunite 12/9/2025 Approved JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 12/9/2025 SGSOV Approved JEFFREY PARD
Enclosure/Fence 12/12/2025 Approved JEFFREY PARD
Final 12/12/2025 OK to Issue CofO JEFFREY PARD