24030 W KILLION ST 91367
Certificate Information: 24030 W KILLION ST 91367
- Application / Permit
- 25047-20000-00951
- Plan Check / Job No.
- B25VN21721
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) 39' X ? POOL WITH 7' X 14' SPA ALL WORK PER STD PLAN# 268 AND ENG DETAILS
- Permit Issued
- Issued on 10/3/2025
- Issuing Office
- Valley
- Current Status
- CofO in Progress on 5/27/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/29/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/5/2025 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 8/8/2025 | SEWADA ZADOORIAN MILAGARDI |
| Building Plans Picked Up | 9/5/2025 | APPLICANT |
| Applicant returned to address corrections | 9/12/2025 | KAMYAR EMAMI |
| Issued | 10/3/2025 | APPLICANT |
| CofO in Progress | 5/27/2026 | GEVORK IPCHYAN |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/3/2025 | SEWADA ZADOORAN MILAGARDI |
Contact Information
| Contractor | Outdoor Pros Builders Inc; Lic. No.: 1088830-B | 6740 FALLBROOK AVE 206 WEST HILLS, CA 91307 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Piping or Gas Test | 1/27/2026 | Not Ready for Inspection | GEVORK IPCHYAN |
| Pre-Gunite | 1/27/2026 | Not Ready for Inspection | GEVORK IPCHYAN |
| Rough-Electrical | 1/27/2026 | Not Ready for Inspection | GEVORK IPCHYAN |
| Rough-Plumbing | 1/27/2026 | Not Ready for Inspection | GEVORK IPCHYAN |
| Pool Piping | 1/28/2026 | Approved | GEVORK IPCHYAN |
| Pre-Gunite | 1/28/2026 | Approved | GEVORK IPCHYAN |
| Rough-Electrical | 1/28/2026 | Approved | GEVORK IPCHYAN |
| Rough-Plumbing | 1/28/2026 | Approved | GEVORK IPCHYAN |
| Special/Order Compliance | 1/28/2026 | Corrections Issued | GEVORK IPCHYAN |
| Grounding or Bonding | 3/10/2026 | Approved | GEVORK IPCHYAN |
| Enclosure/Fence | 5/4/2026 | Corrections Issued | GEVORK IPCHYAN |
| Enclosure/Fence | 5/11/2026 | Approved | GEVORK IPCHYAN |
| Excavation/Setback/Form/Re-Bar | 5/11/2026 | Approved | GEVORK IPCHYAN |
| SGSOV-Seismic Gas S/O Valve | 5/11/2026 | SGSOV Approved | GEVORK IPCHYAN |
| Pool Equipment Noise Test | 5/13/2026 | Approved | ALFREDO FLORES |
| Final | 5/18/2026 | Not Ready for Inspection | TROY SANDERS |
| Final | 5/26/2026 | OK to Issue CofO | GEVORK IPCHYAN |