6332 W COLGATE AVE 90048
Certificate Information: 6332 W COLGATE AVE 90048
- Application / Permit
- 25047-20000-00926
- Plan Check / Job No.
- B25VN21109
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 23'-0" x 13'-0" SWIMMING POOL AND 7'-0" x 13'-0" SPA WITH BAJA PER LA CITY STANDARD PLAN #268.
- Permit Issued
- Issued on 9/15/2025
- Issuing Office
- Current Status
- CofO Issued on 4/21/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/23/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/23/2025 | GIOVANNY CHAVEZ |
| Corrections Issued | 7/23/2025 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 8/5/2025 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 9/15/2025 | YAQUB MIRZA |
| Issued | 9/15/2025 | APPLICANT |
| CofO in Progress | 4/15/2026 | WILBER ROSALES |
| Permit Finaled | 4/21/2026 | RICHARD STEINBACH |
| CofO Issued | 4/21/2026 | RICHARD STEINBACH |
| Permit Finaled | 4/21/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| CPC | Cleared | 7/25/2025 | JASON CHAN |
| Construction near power lines | Cleared | 8/18/2025 | WALTER RAMIREZ |
Contact Information
| Contractor | Titan Builders & Remodeling Inc; Lic. No.: 1002561-C53 | 4872 TOPANGA CANYON BLVD #402 WOODLAND HILLS, CA 91364 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/15/2025 | Not Ready for Inspection | EVAN COOPER |
| Rough-Electrical | 10/15/2025 | Not Ready for Inspection | EVAN COOPER |
| Rough-Plumbing | 10/15/2025 | Not Ready for Inspection | EVAN COOPER |
| Pre-Gunite | 10/17/2025 | Approved | EVAN COOPER |
| Rough-Electrical | 10/17/2025 | Partial Approval | EVAN COOPER |
| Rough-Plumbing | 10/17/2025 | Partial Approval | EVAN COOPER |
| Gas Piping or Gas Test | 12/9/2025 | Approved | JAVIER RAMOS JR |
| Grounding or Bonding | 12/9/2025 | Approved | JAVIER RAMOS JR |
| Enclosure/Fence | 1/12/2026 | Corrections Issued | WILBER ROSALES |
| Excavation/Setback/Form/Re-Bar | 2/13/2026 | Approved | WILBER ROSALES |
| Final | 2/13/2026 | Corrections Issued | WILBER ROSALES |
| Green Building Final | 2/13/2026 | Approved | WILBER ROSALES |
| SGSOV-Seismic Gas S/O Valve | 2/13/2026 | SGSOV Approved | WILBER ROSALES |
| Equipment Noise Level | 2/24/2026 | Not Ready for Inspection | JUAN ESCOTO DELGADO |
| Equipment Noise Level | 2/26/2026 | Approved | MIKE WANG |
| Final | 3/27/2026 | Not Ready for Inspection | WILBER ROSALES |
| Final | 4/6/2026 | Corrections Issued | EVAN COOPER |
| Final | 4/15/2026 | OK to Issue CofO | WILBER ROSALES |