311 N BOWLING GREEN WAY 90049
Certificate Information: 311 N BOWLING GREEN WAY 90049
- Application / Permit
- 25047-20000-00837
- Plan Check / Job No.
- B25VN19108
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 25' x 14' SWIMMING POOL AND 7'x 14' SPA PER LA CITY STANDARD PLAN # 268 AND SUPPLEMENTAL DETAILS PER ENGINEER.
- Permit Issued
- Issued on 7/14/2025
- Issuing Office
- Current Status
- Issued on 7/14/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 7/3/2025 | GIOVANNY CHAVEZ |
| Corrections Issued | 7/3/2025 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 7/8/2025 | KAMYAR EMAMI |
| Plan Check Approved | 7/14/2025 | OMAR GARNICA |
| Issued | 7/14/2025 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/3/2025 | GIOVANNY CHAVEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/3/2025 | Not Ready for Inspection | DANIEL VERA |
| Green Building Rough | 9/3/2025 | Not Ready for Inspection | DANIEL VERA |
| Pre-Gunite | 9/3/2025 | Not Ready for Inspection | DANIEL VERA |
| Rough-Electrical | 9/3/2025 | Not Ready for Inspection | DANIEL VERA |
| Rough-Plumbing | 9/3/2025 | Not Ready for Inspection | DANIEL VERA |
| Excavation/Setback/Form/Re-Bar | 9/4/2025 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 9/4/2025 | Approved | CARLOS MATAMOROS |
| Grounding or Bonding | 9/4/2025 | Approved | CARLOS MATAMOROS |
| Pre-Gunite | 9/4/2025 | Approved | CARLOS MATAMOROS |
| Rough-Electrical | 9/4/2025 | Approved | CARLOS MATAMOROS |
| Rough-Plumbing | 9/4/2025 | Approved | CARLOS MATAMOROS |
| Deputy Shotcrete | 9/5/2025 | Conditional Approval | CARLOS MATAMOROS |
| Grounding or Bonding | 2/11/2026 | Approved | WILBER ROSALES |
| Grounding or Bonding | 2/12/2026 | Partial Approval | EVAN COOPER |
| Enclosure/Fence | 4/20/2026 | Corrections Issued | EVAN COOPER |
| Final | 6/25/2026 | Corrections Issued | EVAN COOPER |
| Green Building Final | 6/25/2026 | Approved | EVAN COOPER |
| Pool Equipment Noise Test | 6/25/2026 | Approved | BRIAN CHRISTIAN |
| SGSOV-Seismic Gas S/O Valve | 6/25/2026 | SGSOV Not Ready | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 6/30/2026 | SGSOV Not Ready | EVAN COOPER |