20551 W EDGEWOOD CT 91311
Certificate Information: 20551 W EDGEWOOD CT 91311
- Application / Permit
- 25047-20000-00748
- Plan Check / Job No.
- B25VN17296
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW POOL AND SPA PER LA STANDARD PLAN# 268 AND SUPPLEMENTAL DETAILS
- Permit Issued
- Issued on 9/19/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/9/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/17/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/23/2025 | JESSE ARELLANO |
| Corrections Issued | 6/23/2025 | JESSE ARELLANO |
| Building Plans Picked Up | 6/26/2025 | APPLICANT |
| Applicant returned to address corrections | 7/14/2025 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 8/21/2025 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 9/19/2025 | ISIS ARGUETA |
| Plan Check Approved | 9/19/2025 | ISIS ARGUETA |
| Issued | 9/19/2025 | APPLICANT |
| CofO in Progress | 1/9/2026 | DAVID SCANTLIN |
| Permit Finaled | 1/9/2026 | JOHN JANSON |
| CofO Issued | 1/9/2026 | JOHN JANSON |
| Permit Finaled | 1/9/2026 | JOHN JANSON |
Permit Application Clearance Information
| "T" removal | Cleared | 7/2/2025 | DORIAN AGUILAR |
| ZA Case | Cleared | 7/9/2025 | DORIAN AGUILAR |
Contact Information
| Contractor | The Green Scene Inc; Lic. No.: 340258-B | 21220 DEVONSHIRE ST STE 102 CHATSWORTH, CA 91311 |
| Engineer | Ganeshwara,, Vela; Lic. No.: GE2736 | 19420 KILFINAN ST PORTER RANCH, CA 91326 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 10/3/2025 | Approved | DAVID SCANTLIN |
| Deputy Shotcrete | 10/8/2025 | Conditional Approval | DAVID SCANTLIN |
| Deck | 10/9/2025 | Approved | DAVID SCANTLIN |
| Enclosure/Fence | 11/24/2025 | Approved | DAVID SCANTLIN |
| Pool Equipment Noise Test | 1/6/2026 | Approved | ALFREDO FLORES |
| Excavation/Setback/Form/Re-Bar | 1/8/2026 | Approved | DAVID SCANTLIN |
| Final | 1/8/2026 | OK to Issue CofO | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 1/8/2026 | SGSOV Approved | DAVID SCANTLIN |