1329 N GENESEE AVE 90046
Certificate Information: 1329 N GENESEE AVE 90046
- Application / Permit
- 25047-20000-00693
- Plan Check / Job No.
- B25VN16170
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW POOL AND SPA PER STANDARD PLAN 268 AND ENGINEER DETAIL
- Permit Issued
- Issued on 7/17/2025
- Issuing Office
- Valley
- Current Status
- Issued on 7/17/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/6/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/6/2025 | ARAMIK SHAHMIRZAIAN |
| Corrections Issued | 6/6/2025 | ARAMIK SHAHMIRZAIAN |
| Plan Check Approved | 7/17/2025 | ALEC MOUSAKHANIAN |
| Issued | 7/17/2025 | APPLICANT |
Permit Application Clearance Information
| Construction near power lines | Cleared | 6/6/2025 | OSCAR CASTRO |
| Construction within easement | Cleared | 6/6/2025 | OSCAR CASTRO |
| HPOZ | Cleared | 7/9/2025 | CHRISTINA PARK |
Contact Information
| Contractor | Athlon Pool Company Inc; Lic. No.: 970093-C53 | 150 S GLENOAKS BLVD #9152 BURBANK, CA 91502 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Piping or Gas Test | 9/4/2025 | Not Ready for Inspection | ROY SPAULDING |
| Pre-Gunite | 9/4/2025 | Corrections Issued | ROY SPAULDING |
| Rough-Electrical | 9/4/2025 | Not Ready for Inspection | ROY SPAULDING |
| Rough-Plumbing | 9/4/2025 | Not Ready for Inspection | ROY SPAULDING |
| Gunite | 9/5/2025 | Approved | BRIAN SULLIVAN |
| Pool Piping | 9/5/2025 | Conditional Approval | BRIAN SULLIVAN |
| Rough-Electrical | 9/5/2025 | Approved | BRIAN SULLIVAN |
| Rough-Plumbing | 9/5/2025 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Shotcrete | 9/8/2025 | Conditional Approval | ROY SPAULDING |
| Deck | 11/14/2025 | Not Ready for Inspection | ROY SPAULDING |
| Deck | 1/20/2026 | Approved | SCOTT FINNILA |
| Enclosure/Fence | 3/17/2026 | No Access for Inspection | ROY SPAULDING |
| Enclosure/Fence | 3/19/2026 | Approved | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 3/26/2026 | SGSOV Not Ready | ROY SPAULDING |
| Excavation/Setback/Form/Re-Bar | 4/24/2026 | Approved | ROY SPAULDING |
| Pre-Gunite | 4/24/2026 | Approved | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 4/24/2026 | SGSOV Not Ready | ROY SPAULDING |
| Final | 4/30/2026 | Not Ready for Inspection | ROY SPAULDING |
| Pool Equipment Noise Test | 4/30/2026 | Approved | MIKE WANG |
| SGSOV-Seismic Gas S/O Valve | 4/30/2026 | SGSOV Not Ready | ROY SPAULDING |
| Final | 5/14/2026 | Conditional Approval | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 5/14/2026 | SGSOV Approved | ROY SPAULDING |