2764 S COLBY AVE 90064
Certificate Information: 2764 S COLBY AVE 90064
- Application / Permit
- 25047-20000-00692
- Plan Check / Job No.
- B25VN16166
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 42' X 11' SWIMMING POOL PER LA CITY STANDARD PLAN #268 AND ENGINEERED DETAIL.
- Permit Issued
- Issued on 9/8/2025
- Issuing Office
- Valley
- Current Status
- Issued on 9/8/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/6/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/6/2025 | GURUNATH NESARAJAH |
| Corrections Issued | 6/6/2025 | GURUNATH NESARAJAH |
| Issued | 9/8/2025 | APPLICANT |
Permit Application Clearance Information
| Construction near power lines | Cleared | 9/5/2025 | RIDWAN HARDY |
| Construction within easement | Cleared | 9/5/2025 | RIDWAN HARDY |
Contact Information
| Contractor | J Designs Pool & Spa Inc; Lic. No.: 938120-C53 | 5250 LANKERSHIM BLVD SUITE 500 NORTH HOLLYWOOD, CA 91601 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/14/2025 | Conditional Approval | KIRK SANDERS |
| Final | 11/14/2025 | Corrections Issued | KIRK SANDERS |
| Grounding or Bonding | 11/14/2025 | Partial Approval | KIRK SANDERS |
| Pre-Gunite | 11/14/2025 | Conditional Approval | KIRK SANDERS |
| Rough-Electrical | 11/14/2025 | Partial Approval | KIRK SANDERS |
| Rough-Plumbing | 11/14/2025 | Partial Approval | KIRK SANDERS |
| Gas Piping or Gas Test | 12/11/2025 | Corrections Issued | KIRK SANDERS |
| Grounding or Bonding | 12/11/2025 | Partial Approval | KIRK SANDERS |
| Pool Piping | 12/11/2025 | Approved | KIRK SANDERS |
| Rough-Electrical | 12/11/2025 | Approved | KIRK SANDERS |
| Rough-Plumbing | 12/11/2025 | Approved | KIRK SANDERS |
| Deck | 4/16/2026 | Approved | EUGENE CASSIDY |