22518 W BURBANK BLVD 91367

Certificate Information: 22518 W BURBANK BLVD 91367

Application / Permit
25047-20000-00675
Plan Check / Job No.
B25VN15800
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 30' X 20' POOL AND 10'X9' SPA WITH BAJA PER STANDARD PLAN 268. (1 OF 2)
Permit Issued
Issued on 7/30/2025
Issuing Office
Current Status
CofO Issued on 6/25/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/3/2025 APPLICANT
Assigned to Plan Check Engineer 6/3/2025 ALEC MOUSAKHANIAN
Corrections Issued 6/3/2025 ALEC MOUSAKHANIAN
Issued 7/30/2025 APPLICANT
CofO in Progress 6/15/2026 GEVORK IPCHYAN
Permit Finaled 6/25/2026 JOHN JANSON
CofO Issued 6/25/2026 JOHN JANSON
Permit Finaled 6/25/2026 JOHN JANSON

Permit Application Clearance Information

Construction near power lines Cleared 7/29/2025 GEVORK KARAPETYAN
Construction within easement Cleared 7/29/2025 GEVORK KARAPETYAN

Contact Information

Contractor American Way Remodeling Inc; Lic. No.: 986644-B 22718 MACGARLANE DRIVE      WOODLAND HILLS, CA 91364
Engineer Thompson,, Matthew Gregory; Lic. No.: C86051 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/19/2025 Approved GEVORK IPCHYAN
Pre-Gunite 8/19/2025 Approved GEVORK IPCHYAN
Rough-Electrical 8/19/2025 Not Ready for Inspection GEVORK IPCHYAN
Rough-Plumbing 8/19/2025 Approved GEVORK IPCHYAN
Deputy Shotcrete 8/29/2025 Conditional Approval ROBERT GOLD
Grounding or Bonding 3/9/2026 Approved GEVORK IPCHYAN
Enclosure/Fence 5/4/2026 Approved GEVORK IPCHYAN
Equipment Noise Level 5/26/2026 Not Ready for Inspection AGUSTIN ALVAREZMORALES
Final 5/26/2026 Not Ready for Inspection GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 5/26/2026 SGSOV Not Ready GEVORK IPCHYAN
Equipment Noise Level 5/28/2026 Approved ALFREDO FLORES
Final 5/29/2026 Corrections Issued GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 5/29/2026 SGSOV Approved GEVORK IPCHYAN
ELECTRICAL-Final 6/15/2026 Approved GEVORK IPCHYAN
Final 6/15/2026 OK to Issue CofO GEVORK IPCHYAN