2932 N NICADA DR 90077

Certificate Information: 2932 N NICADA DR 90077

Application / Permit
25047-20000-00593
Plan Check / Job No.
B25VN13820
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
POOL REMODEL PER STANDARD PLAN 268 AND ENGINEERING DETAILS 551 & 640.
Permit Issued
Issued on 6/18/2025
Issuing Office
Current Status
CofO Issued on 1/6/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/15/2025 APPLICANT
Assigned to Plan Check Engineer 5/21/2025 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 5/27/2025 SEWADA ZADOORIAN MILAGARDI
Building Plans Picked Up 5/27/2025 APPLICANT
Plan Check Approved 6/18/2025 SERGIO MUNIZ
Issued 6/18/2025 APPLICANT
CofO in Progress 1/6/2026 CARLOS MATAMOROS
Permit Finaled 1/6/2026 RICHARD STEINBACH
CofO Issued 1/6/2026 RICHARD STEINBACH
Permit Finaled 1/6/2026 RICHARD STEINBACH

Permit Application Clearance Information

Miscellaneous Cleared 5/28/2025 NATHAN ROMINE
Specific Plan Cleared 5/28/2025 NATHAN ROMINE
Grading Pre-Inspection Cleared 6/18/2025 ROBERT PINA

Contact Information

Contractor Green Team Construction Group Inc; Lic. No.: 1103216-B 19137 DELANO ST      TARZANA, CA 91335
Engineer Thompson,, Matthew Gregory; Lic. No.: C86051 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/18/2025 Approved SEAN HAUPT
Pre-Gunite 7/18/2025 Approved SEAN HAUPT
Rough-Electrical 7/18/2025 Approved SEAN HAUPT
Rough-Plumbing 7/18/2025 Approved SEAN HAUPT
Deputy Shotcrete 7/22/2025 Partial Approval SEAN HAUPT
Deck 8/20/2025 Approved SEAN HAUPT
Grounding or Bonding 8/20/2025 Approved SEAN HAUPT
Special/Order Compliance 8/20/2025 Approved SEAN HAUPT
Enclosure/Fence 9/25/2025 Approved SEAN HAUPT
Special/Order Compliance 9/25/2025 Approved SEAN HAUPT
Final 12/17/2025 No Access for Inspection CARLOS MATAMOROS
Final 12/31/2025 Corrections Issued CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 12/31/2025 SGSOV Not Ready CARLOS MATAMOROS
ELECTRICAL-Final 1/5/2026 Approved CARLOS MATAMOROS
Final 1/5/2026 OK to Issue CofO CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 1/5/2026 SGSOV Approved CARLOS MATAMOROS