10765 N OWENS PL 91042
Certificate Information: 10765 N OWENS PL 91042
- Application / Permit
- 25047-20000-00570
- Plan Check / Job No.
- B25VN13313
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- New irregular shaped Spa. Work per Std detail 268 and engineer detail
- Permit Issued
- Issued on 7/28/2025
- Issuing Office
- Current Status
- Issued on 7/28/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/13/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/15/2025 | NAREG ATARIAN |
| Corrections Issued | 5/16/2025 | NAREG ATARIAN |
| Applicant returned to address corrections | 5/29/2025 | ISIS ARGUETA |
| Applicant returned to address corrections | 6/14/2025 | NAREG ATARIAN |
| Applicant returned to address corrections | 6/21/2025 | NAREG ATARIAN |
| Applicant returned to address corrections | 6/24/2025 | NAREG ATARIAN |
| Plan Check Approved | 6/30/2025 | NAREG ATARIAN |
| No Progress | 7/9/2025 | NAREG ATARIAN |
| Plan Check Approved | 7/9/2025 | NAREG ATARIAN |
| Plan Check Approved | 7/24/2025 | JAZMIN OLMOS |
| No Progress | 7/24/2025 | JAZMIN OLMOS |
| Plan Check Approved | 7/24/2025 | NAREG ATARIAN |
| Issued | 7/28/2025 | APPLICANT |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 5/16/2025 | CHARLES POWELL |
| ZA Case | Cleared | 6/27/2025 | DORIAN AGUILAR |
Contact Information
| Contractor | Triton Pools & Spas Inc; Lic. No.: 1130616-C53 | 14379 HERRON ST SYLMAR, CA 91342 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Green Building Rough | 7/30/2025 | Not Ready for Inspection | WILLIAM WREN |
| Pre-Gunite | 7/30/2025 | Corrections Issued | WILLIAM WREN |
| Gunite | 8/1/2025 | Corrections Issued | WILLIAM WREN |
| Green Building Rough | 8/8/2025 | Approved | WILLIAM WREN |
| Pre-Gunite | 8/8/2025 | Approved | WILLIAM WREN |
| Deck | 8/14/2025 | Corrections Issued | WILLIAM WREN |
| Deck | 8/28/2025 | Approved | WILLIAM WREN |
| Enclosure/Fence | 9/5/2025 | Approved | WILLIAM WREN |
| Equipment Noise Level | 9/5/2025 | Approved | FELIPE PENICHE |
| Excavation/Setback/Form/Re-Bar | 9/25/2025 | Not Ready for Inspection | WILLIAM WREN |
| Final | 9/25/2025 | Not Ready for Inspection | WILLIAM WREN |
| Green Building Final | 9/25/2025 | Not Ready for Inspection | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 9/25/2025 | SGSOV Not Ready | WILLIAM WREN |
| Excavation/Setback/Form/Re-Bar | 9/26/2025 | Approved | WILLIAM WREN |
| Final | 9/26/2025 | Conditional Approval | WILLIAM WREN |
| Green Building Final | 9/26/2025 | Approved | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 9/26/2025 | SGSOV Approved | WILLIAM WREN |