1550 S REEVES ST 90035
Certificate Information: 1550 S REEVES ST 90035
- Application / Permit
- 25047-20000-00556
- Plan Check / Job No.
- B25VN12910
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- PROPOSED REMODEL OF EXISTING SWIMMING POOL - BACKFILL 16'X20'6" POR OF EX POOL (25030-20000-02910) , RESHAPE THE EXISTING POOL W/ NEW SPA & BAJA PER PLAN PER CITY STD PLAN #268 & SUPPLEMENTAL ENGR DETAILS.
- Permit Issued
- Issued on 6/4/2025
- Issuing Office
- Current Status
- CofO Issued on 11/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/8/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/8/2025 | HAYATO TSUCHIYA |
| Corrections Issued | 5/8/2025 | HAYATO TSUCHIYA |
| Plan Check Approved | 6/4/2025 | SARKIS HARABEDIAN |
| Issued | 6/4/2025 | APPLICANT |
| CofO in Progress | 11/21/2025 | ASHLEY THOMPSON |
| Permit Finaled | 11/29/2025 | RICHARD STEINBACH |
| CofO Issued | 11/29/2025 | RICHARD STEINBACH |
| Permit Finaled | 11/29/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 5/22/2025 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 6/4/2025 | LANNY MERRICK |
Contact Information
| Contractor | P & S Construction Experts; Lic. No.: 1109254-B | 15701 SHERMAN WAY UNITE 14604 VAN NUYS, CA 91406 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grounding or Bonding | 6/26/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Pool Piping | 6/26/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Pre-Gunite | 6/26/2025 | Corrections Issued | ASHLEY THOMPSON |
| Rough-Electrical | 6/26/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Rough-Plumbing | 6/26/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Deputy Drilled-In Anchors | 6/27/2025 | Conditional Approval | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 6/30/2025 | Approved | ARAM AVEDISIAN |
| Grounding or Bonding | 6/30/2025 | Partial Approval | ARAM AVEDISIAN |
| Pool Piping | 6/30/2025 | Approved | ARAM AVEDISIAN |
| Pre-Gunite | 6/30/2025 | Conditional Approval | ARAM AVEDISIAN |
| Rough-Electrical | 6/30/2025 | Approved | ARAM AVEDISIAN |
| Grounding or Bonding | 8/28/2025 | Approved | EVAN COOPER |
| Enclosure/Fence | 10/23/2025 | Approved | EVAN COOPER |
| Final | 11/7/2025 | Corrections Issued | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 11/7/2025 | SGSOV Approved | ASHLEY THOMPSON |
| Final | 11/20/2025 | OK to Issue CofO | ASHLEY THOMPSON |