1550 S REEVES ST 90035

Certificate Information: 1550 S REEVES ST 90035

Application / Permit
25047-20000-00556
Plan Check / Job No.
B25VN12910
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
PROPOSED REMODEL OF EXISTING SWIMMING POOL - BACKFILL 16'X20'6" POR OF EX POOL (25030-20000-02910) , RESHAPE THE EXISTING POOL W/ NEW SPA & BAJA PER PLAN PER CITY STD PLAN #268 & SUPPLEMENTAL ENGR DETAILS.
Permit Issued
Issued on 6/4/2025
Issuing Office
Current Status
CofO Issued on 11/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/8/2025 APPLICANT
Assigned to Plan Check Engineer 5/8/2025 HAYATO TSUCHIYA
Corrections Issued 5/8/2025 HAYATO TSUCHIYA
Plan Check Approved 6/4/2025 SARKIS HARABEDIAN
Issued 6/4/2025 APPLICANT
CofO in Progress 11/21/2025 ASHLEY THOMPSON
Permit Finaled 11/29/2025 RICHARD STEINBACH
CofO Issued 11/29/2025 RICHARD STEINBACH
Permit Finaled 11/29/2025 RICHARD STEINBACH

Permit Application Clearance Information

Construction near power lines Cleared 5/22/2025 RIDWAN HARDY
Grading Pre-Inspection Cleared 6/4/2025 LANNY MERRICK

Contact Information

Contractor P & S Construction Experts; Lic. No.: 1109254-B 15701 SHERMAN WAY UNITE 14604      VAN NUYS, CA 91406
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grounding or Bonding 6/26/2025 Not Ready for Inspection ASHLEY THOMPSON
Pool Piping 6/26/2025 Not Ready for Inspection ASHLEY THOMPSON
Pre-Gunite 6/26/2025 Corrections Issued ASHLEY THOMPSON
Rough-Electrical 6/26/2025 Not Ready for Inspection ASHLEY THOMPSON
Rough-Plumbing 6/26/2025 Not Ready for Inspection ASHLEY THOMPSON
Deputy Drilled-In Anchors 6/27/2025 Conditional Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 6/30/2025 Approved ARAM AVEDISIAN
Grounding or Bonding 6/30/2025 Partial Approval ARAM AVEDISIAN
Pool Piping 6/30/2025 Approved ARAM AVEDISIAN
Pre-Gunite 6/30/2025 Conditional Approval ARAM AVEDISIAN
Rough-Electrical 6/30/2025 Approved ARAM AVEDISIAN
Grounding or Bonding 8/28/2025 Approved EVAN COOPER
Enclosure/Fence 10/23/2025 Approved EVAN COOPER
Final 11/7/2025 Corrections Issued ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 11/7/2025 SGSOV Approved ASHLEY THOMPSON
Final 11/20/2025 OK to Issue CofO ASHLEY THOMPSON