4447 N MATILIJA AVE 91423
Certificate Information: 4447 N MATILIJA AVE 91423
- Application / Permit
- 25047-20000-00522
- Plan Check / Job No.
- B25VN12123
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 16' X 30' POOL AND SPA PER STANDARD PLANS.
- Permit Issued
- Issued on 5/1/2025
- Issuing Office
- Current Status
- CofO Issued on 4/30/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/1/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/1/2025 | ARAMIK SHAHMIRZAIAN |
| Issued | 5/1/2025 | APPLICANT |
| CofO in Progress | 3/23/2026 | MISAEL ESPARZA |
| CofO Issued | 4/30/2026 | RUBEN SALAS |
| Permit Finaled | 4/30/2026 | RUBEN SALAS |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/16/2025 | Corrections Issued | MISAEL ESPARZA |
| Rough-Electrical | 5/16/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Rough-Plumbing | 5/16/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Pool Piping | 5/21/2025 | Approved | MISAEL ESPARZA |
| Pre-Gunite | 5/21/2025 | Corrections Issued | MISAEL ESPARZA |
| Rough-Electrical | 5/21/2025 | Partial Approval | MISAEL ESPARZA |
| Rough-Plumbing | 5/21/2025 | Approved | MISAEL ESPARZA |
| Deputy Shotcrete | 5/27/2025 | Conditional Approval | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 8/8/2025 | SGSOV Not Ready | MISAEL ESPARZA |
| Gas Piping or Gas Test | 8/15/2025 | Partial Approval | JAVIER RAMOS JR |
| Deck | 11/26/2025 | Approved | MISAEL ESPARZA |
| Enclosure/Fence | 2/19/2026 | Partial Inspection | JAVIER RAMOS JR |
| Equipment Noise Level | 2/24/2026 | Approved | FELIPE PENICHE |
| Excavation/Setback/Form/Re-Bar | 2/24/2026 | Approved | JACK KARGODORIAN |
| Final | 2/24/2026 | Partial Approval | JACK KARGODORIAN |
| Pool Equipment Noise Test | 2/24/2026 | Approved | FELIPE PENICHE |
| Pre-Gunite | 2/24/2026 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 2/24/2026 | SGSOV Approved | JACK KARGODORIAN |
| Final | 3/20/2026 | OK to Issue CofO | MISAEL ESPARZA |