23010 W HARTLAND ST 91307

Certificate Information: 23010 W HARTLAND ST 91307

Application / Permit
25047-20000-00518
Plan Check / Job No.
B25VN12066
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW POOL AND SPA PER LA CITY STANDARD PLAN #268.
Permit Issued
Issued on 5/7/2025
Issuing Office
Current Status
CofO Issued on 7/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/30/2025 APPLICANT
Assigned to Plan Check Engineer 4/30/2025 ISIS ARGUETA
Plan Check Approved 4/30/2025 ISIS ARGUETA
No Progress 5/6/2025 GIOVANNY CHAVEZ
Plan Check Approved 5/7/2025 SERGIO MUNIZ
Issued 5/7/2025 APPLICANT
CofO in Progress 7/3/2025 GEVORK IPCHYAN
Permit Finaled 7/18/2025 DANIEL ORRANTE
CofO Issued 7/18/2025 DANIEL ORRANTE

Permit Application Clearance Information

Construction near power lines Cleared 5/7/2025 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/16/2025 Partial Approval TROY SANDERS
Gas Piping or Gas Test 5/28/2025 Approved GEVORK IPCHYAN
Gunite 5/28/2025 Approved GEVORK IPCHYAN
Pool Piping 5/28/2025 Approved GEVORK IPCHYAN
Rough-Electrical 5/28/2025 Approved GEVORK IPCHYAN
Rough-Plumbing 5/28/2025 Approved GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 5/28/2025 SGSOV Not Ready GEVORK IPCHYAN
Deputy Shotcrete 5/30/2025 Conditional Approval TROY SANDERS
Deputy Shotcrete 6/2/2025 Conditional Approval TROY SANDERS
Deck 6/9/2025 Approved TROY SANDERS
Enclosure/Fence 6/20/2025 Approved GEVORK IPCHYAN
Excavation/Setback/Form/Re-Bar 6/25/2025 Approved GEVORK IPCHYAN
Final 6/25/2025 Partial Approval GEVORK IPCHYAN
Green Building Final 6/25/2025 Approved GEVORK IPCHYAN
Green Building Rough 6/25/2025 Approved GEVORK IPCHYAN
Pool Equipment Noise Test 6/25/2025 Approved ALFREDO FLORES
Pre-Gunite 6/25/2025 Approved GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 6/25/2025 SGSOV Approved GEVORK IPCHYAN
Final 7/2/2025 OK to Issue CofO GEVORK IPCHYAN