8672 N ENCINO AVE 91325
Certificate Information: 8672 N ENCINO AVE 91325
- Application / Permit
- 25047-20000-00512
- Plan Check / Job No.
- B25VN11938
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 32'-0" x 17'-0" WITH A 9'-6" x 8'-11" SPA PER LA CITY STANDARD PLAN #265.
- Permit Issued
- Issued on 5/1/2025
- Issuing Office
- Current Status
- CofO Issued on 11/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/29/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/30/2025 | GIOVANNY CHAVEZ |
| Plan Check Approved | 5/1/2025 | GIOVANNY CHAVEZ |
| Issued | 5/1/2025 | APPLICANT |
| CofO in Progress | 11/13/2025 | NICHOLAS TROWBRIDGE |
| Permit Finaled | 11/21/2025 | RUBEN SALAS |
| CofO Issued | 11/21/2025 | RUBEN SALAS |
| Permit Finaled | 11/21/2025 | RUBEN SALAS |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pool Piping | 5/22/2025 | Partial Approval | KEVIN BERBERYAN |
| Pre-Gunite | 5/22/2025 | Conditional Approval | KEVIN BERBERYAN |
| Special/Order Compliance | 5/22/2025 | Partial Inspection | RAUL OLAGI |
| Deputy Shotcrete | 5/23/2025 | Conditional Approval | RAUL OLAGI |
| Deck | 9/29/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Grounding or Bonding | 9/29/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Deck | 9/30/2025 | Approved | NICHOLAS TROWBRIDGE |
| Enclosure/Fence | 11/6/2025 | Approved | NICHOLAS TROWBRIDGE |
| Pool Equipment Noise Test | 11/6/2025 | Approved | NICHOLAS TROWBRIDGE |
| Final | 11/12/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Green Building Final | 11/12/2025 | Approved | NICHOLAS TROWBRIDGE |
| Pre-Gunite | 11/12/2025 | Approved | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 11/12/2025 | SGSOV Approved | NICHOLAS TROWBRIDGE |
| Excavation/Setback/Form/Re-Bar | 11/13/2025 | Approved | NICHOLAS TROWBRIDGE |
| Final | 11/13/2025 | OK to Issue CofO | NICHOLAS TROWBRIDGE |
| Green Building Rough | 11/13/2025 | Approved | NICHOLAS TROWBRIDGE |