5032 N BLUEBELL AVE 91607
Certificate Information: 5032 N BLUEBELL AVE 91607
- Application / Permit
- 25047-20000-00375
- Plan Check / Job No.
- B25VN08529
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- New 24' x 14' Pool and Spa. Per Standard details (268)
- Permit Issued
- Issued on 4/11/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/13/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/28/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/28/2025 | NAREG ATARIAN |
| Corrections Issued | 3/28/2025 | NAREG ATARIAN |
| Plan Check Approved | 4/11/2025 | NAREG ATARIAN |
| Issued | 4/11/2025 | APPLICANT |
| CofO in Progress | 3/12/2026 | RAUL OLAGI |
| Permit Finaled | 3/13/2026 | RUBEN SALAS |
| CofO Issued | 3/13/2026 | RUBEN SALAS |
| Permit Finaled | 3/13/2026 | RUBEN SALAS |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Pristine Construction Inc; Lic. No.: 939885-B | 14320 VENTURA BL #320 SHERMAN OAKS, CA 91423 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/18/2025 | Approved | GAREN HAYRAPETYAN |
| Gas Piping or Gas Test | 4/24/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Pool Piping | 4/24/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Rough-Electrical | 4/24/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Rough-Plumbing | 4/24/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Gas Piping or Gas Test | 4/25/2025 | Corrections Issued | OGANES TARAKHCHYAN |
| Pool Piping | 4/25/2025 | Approved | OGANES TARAKHCHYAN |
| Pre-Gunite | 4/25/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Rough-Plumbing | 4/25/2025 | Approved | OGANES TARAKHCHYAN |
| Enclosure/Fence | 9/10/2025 | Approved | OGANES TARAKHCHYAN |
| Pool Equipment Noise Test | 9/17/2025 | Approved | FELIPE PENICHE |
| Final | 9/22/2025 | Corrections Issued | WAYNE REGESTER |
| Green Building Final | 9/22/2025 | Approved | WAYNE REGESTER |
| Green Building Rough | 9/22/2025 | Approved | WAYNE REGESTER |
| Pre-Gunite | 9/22/2025 | Approved | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 9/22/2025 | SGSOV Not Ready | WAYNE REGESTER |
| Final | 9/29/2025 | Not Ready for Inspection | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 9/29/2025 | SGSOV Not Ready | WAYNE REGESTER |
| Final | 10/3/2025 | OK to Issue CofO | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 10/3/2025 | SGSOV Approved | OGANES TARAKHCHYAN |