616 S ARDEN BLVD 90005
Certificate Information: 616 S ARDEN BLVD 90005
- Application / Permit
- 25047-20000-00247
- Plan Check / Job No.
- B25VN05291
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- ADD 8'-0" x 11'-0" SPA TO EXISTING POOL PER STANDARD PLAN #268 AND ENGR DETAIL
- Permit Issued
- Issued on 3/11/2025
- Issuing Office
- Current Status
- CofO Issued on 2/23/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/27/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/27/2025 | ISIS ARGUETA |
| Corrections Issued | 2/27/2025 | ISIS ARGUETA |
| Plan Check Approved | 3/11/2025 | GIOVANNY CHAVEZ |
| Issued | 3/11/2025 | APPLICANT |
| CofO in Progress | 2/19/2026 | RONNIE MINDANAO |
| Permit Finaled | 2/23/2026 | DEROLD HAUFF |
| CofO Issued | 2/23/2026 | DEROLD HAUFF |
| Permit Finaled | 2/23/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| HPOZ | Cleared | 3/5/2025 | DANIEL CORONADO |
| Specific Plan | Cleared | 3/5/2025 | DANIEL CORONADO |
Contact Information
| Contractor | H & H Pools And Spa Inc; Lic. No.: 1056975-C53 | 10058 MEMORY PARK AVE MISSION HILLS, CA 91345 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/7/2025 | Approved | RONNIE MINDANAO |
| Pre-Gunite | 5/7/2025 | Approved | RONNIE MINDANAO |
| Enclosure/Fence | 6/30/2025 | Corrections Issued | ARTHUR NEGRETE |
| Enclosure/Fence | 7/7/2025 | Approved | RONNIE MINDANAO |
| Pool Equipment Noise Test | 7/15/2025 | Not Ready for Inspection | JUAN ESCOTO DELGADO |
| SGSOV-Seismic Gas S/O Valve | 7/16/2025 | SGSOV Not Ready | RONNIE MINDANAO |
| Pool Equipment Noise Test | 7/22/2025 | Approved | JUAN ESCOTO DELGADO |
| Final | 7/23/2025 | Corrections Issued | RONNIE MINDANAO |
| Green Building Final | 7/23/2025 | Approved | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 7/23/2025 | SGSOV Approved | RONNIE MINDANAO |
| Final | 2/6/2026 | OK to Issue CofO | RONNIE MINDANAO |