2427 N PARK OAK DR 90068
Certificate Information: 2427 N PARK OAK DR 90068
- Application / Permit
- 25047-20000-00221
- Plan Check / Job No.
- B25VN04749
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- ADDITION OF CIRCULAR SPA TO THE EXISTING IRREGULAR SHAPED POOL AND REMODEL THE POOL TO REDUCE THE DEPTH TO 6' - PER LA CITY STANDARD PLAN AND SUPPLEMENTARY ENGINEERED DETAILS
- Permit Issued
- Issued on 7/15/2025
- Issuing Office
- Valley
- Current Status
- Issued on 7/15/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/24/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/27/2025 | DANIEL ABRAMYAN |
| Corrections Issued | 3/4/2025 | DANIEL ABRAMYAN |
| Quality Review Completed | 3/4/2025 | OMID HEDAYAT |
| Building Plans Picked Up | 3/18/2025 | APPLICANT |
| Applicant returned to address corrections | 6/20/2025 | DANIEL ABRAMYAN |
| Plan Check Approved | 7/3/2025 | DANIEL ABRAMYAN |
| Issued | 7/15/2025 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/20/2025 | DANIEL ABRAMYAN |
| Hold | Cleared | 10/29/2025 | SANDRA SOH |
Contact Information
| Contractor | Champion Pools Inc; Lic. No.: 1105426-C53 | 13840 PAXTON ST PACOIMA, CA 91331 |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Final | 7/17/2026 |
Inspection Request History
| Pre-Inspection | 7/16/2025 | Corrections Issued | CRAIG VAUGHAN |
| Pool Piping | 7/22/2025 | Partial Approval | CRAIG VAUGHAN |
| Rough-Plumbing | 7/22/2025 | Partial Approval | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 10/30/2025 | Corrections Issued | CRAIG VAUGHAN |
| Piling/Pier/Caisson | 11/3/2025 | Partial Approval | CRAIG VAUGHAN |
| Deputy Other (see comments) | 11/4/2025 | Partial Approval | SCOTT FINNILA |
| Deputy Other (see comments) | 11/5/2025 | Conditional Approval | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 11/7/2025 | Approved | CRAIG VAUGHAN |
| Pre-Gunite | 12/19/2025 | Corrections Issued | CRAIG VAUGHAN |
| Deputy Shotcrete | 12/22/2025 | Conditional Approval | CRAIG VAUGHAN |
| Enclosure/Fence | 3/20/2026 | Corrections Issued | CRAIG VAUGHAN |
| Grounding or Bonding | 3/24/2026 | Partial Approval | CRAIG VAUGHAN |
| Enclosure/Fence | 3/26/2026 | Approved | CRAIG VAUGHAN |
| Pool Equipment Noise Test | 3/31/2026 | Approved | MIKE WANG |
| Final | 4/1/2026 | Corrections Issued | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 4/1/2026 | SGSOV Approved | CRAIG VAUGHAN |