12406 W LA MAIDA ST 91607

Certificate Information: 12406 W LA MAIDA ST 91607

Application / Permit
25047-20000-00185
Plan Check / Job No.
B25VN03916
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 18' X 12' POOL PER STANDARD PLANS AND SUPPLEMNTAL ENGINERING DETAILS.
Permit Issued
Issued on 2/25/2025
Issuing Office
Valley
Current Status
CofO Issued on 11/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/14/2025 APPLICANT
Assigned to Plan Check Engineer 2/14/2025 ARAMIK SHAHMIRZAIAN
Plan Check Approved 2/14/2025 ARAMIK SHAHMIRZAIAN
Issued 2/25/2025 APPLICANT
CofO in Progress 10/21/2025 OGANES TARAKHCHYAN
Permit Finaled 11/13/2025 RUBEN SALAS
CofO Issued 11/13/2025 RUBEN SALAS
Permit Finaled 11/13/2025 RUBEN SALAS

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,
Engineer Thompson,, Matthew Gregory; Lic. No.: C86051 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/28/2025 No Access for Inspection OGANES TARAKHCHYAN
Grounding or Bonding 2/28/2025 No Access for Inspection OGANES TARAKHCHYAN
Pre-Gunite 2/28/2025 No Access for Inspection OGANES TARAKHCHYAN
Pre-Gunite 3/3/2025 Approved CHRISTOPHE COCHRAN
Gas Piping or Gas Test 4/17/2025 Corrections Issued GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 4/17/2025 SGSOV Not Ready GAREN HAYRAPETYAN
Enclosure/Fence 7/8/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Excavation/Setback/Form/Re-Bar 8/27/2025 Not Ready for Inspection OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 8/27/2025 SGSOV Not Ready OGANES TARAKHCHYAN
Enclosure/Fence 8/29/2025 Approved OGANES TARAKHCHYAN
Pool Equipment Noise Test 9/16/2025 Approved FELIPE PENICHE
Final 9/22/2025 Corrections Issued JOSE AVILA
Excavation/Setback/Form/Re-Bar 10/6/2025 Approved OGANES TARAKHCHYAN
Final 10/6/2025 OK to Issue CofO OGANES TARAKHCHYAN
Pre-Gunite 10/6/2025 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 10/6/2025 SGSOV Approved OGANES TARAKHCHYAN