9064 N LEV AVE 91331

Certificate Information: 9064 N LEV AVE 91331

Application / Permit
25047-20000-00182
Plan Check / Job No.
B25VN03856
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 21' X 12' SWIMMING POOL AND 6' X 6' SPA PER STANDARD PLAN #265.
Permit Issued
Issued on 3/18/2025
Issuing Office
Current Status
CofO in Progress on 10/31/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/13/2025 APPLICANT
Assigned to Plan Check Engineer 2/21/2025 JEROME MAGAT PALMA
Corrections Issued 2/22/2025 JEROME MAGAT PALMA
Building Plans Picked Up 2/25/2025 APPLICANT
Issued 3/18/2025 APPLICANT
CofO in Progress 10/31/2025 JACK KARGODORIAN
No Progress 10/31/2025 JACK KARGODORIAN
CofO in Progress 10/31/2025 JACK KARGODORIAN
CofO in Progress 10/31/2025 JACK KARGODORIAN

Permit Application Clearance Information

Construction near power lines Cleared 3/11/2025 GEVORK KARAPETYAN
Construction within easement Cleared 3/11/2025 GEVORK KARAPETYAN

Contact Information

Contractor Gwp Builders Inc; Lic. No.: 974163-B 5632 VAN NUYS BLVD #427      VAN NUYS, CA 91401
Engineer Zhang,, Yao; Lic. No.: C74572 538 ROCCO CIRCLE      CORONA, CA 92882

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/17/2025 Approved VINCENT HANLEY
Gas Piping or Gas Test 4/17/2025 Approved VINCENT HANLEY
Pre-Gunite 4/17/2025 Approved VINCENT HANLEY
Rough-Electrical 4/17/2025 Approved VINCENT HANLEY
Deputy Shotcrete 4/25/2025 Conditional Approval RAUL OLAGI
Deck 7/21/2025 Approved JACK KARGODORIAN
Enclosure/Fence 9/11/2025 Corrections Issued VINCENT HANLEY
Enclosure/Fence 10/9/2025 Corrections Issued VINCENT HANLEY
Enclosure/Fence 10/16/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Enclosure/Fence 10/23/2025 Approved VINCENT HANLEY
Final 10/30/2025 Not Ready for Inspection JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 10/30/2025 SGSOV Approved JACK KARGODORIAN
Pool Equipment Noise Test 11/5/2025 Approved FELIPE PENICHE
Final 11/6/2025 Conditional Approval DAVID MATSON