17237 W SUNBURST ST 91325
Certificate Information: 17237 W SUNBURST ST 91325
- Application / Permit
- 25047-20000-00181
- Plan Check / Job No.
- B25VN03783
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- eplan NEW POOL AND SPA PER STANDARD PLAN 268
- Permit Issued
- Issued on 4/29/2025
- Issuing Office
- Current Status
- CofO in Progress on 5/9/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/13/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2025 | ALEC MOUSAKHANIAN |
| Corrections Issued | 2/14/2025 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 3/10/2025 | SARKIS HARABEDIAN |
| Plan Check Approved | 4/17/2025 | ALEC MOUSAKHANIAN |
| Issued | 4/29/2025 | APPLICANT |
| CofO in Progress | 5/9/2026 | KEVIN BERBERYAN |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/13/2025 | Corrections Issued | KEVIN BERBERYAN |
| Pool Piping | 5/13/2025 | Approved | KEVIN BERBERYAN |
| Excavation/Setback/Form/Re-Bar | 5/16/2025 | Approved | KEVIN BERBERYAN |
| Pool Piping | 5/16/2025 | Partial Inspection | KEVIN BERBERYAN |
| Gas Piping or Gas Test | 6/2/2025 | Approved | VINCENT HANLEY |
| Pre-Gunite | 6/2/2025 | Approved | VINCENT HANLEY |
| Enclosure/Fence | 3/10/2026 | Corrections Issued | JOSE AVILA |
| Grounding or Bonding | 3/31/2026 | Approved | CHRISTOPHER ROJAS |
| Enclosure/Fence | 4/20/2026 | Approved | CHRISTOPHE COCHRAN |
| Final | 4/30/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Pool Equipment Noise Test | 4/30/2026 | Approved | FELIPE PENICHE |
| SGSOV-Seismic Gas S/O Valve | 4/30/2026 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Final | 5/8/2026 | OK to Issue CofO | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 5/8/2026 | SGSOV Approved | KEVIN BERBERYAN |