1572 S CARDIFF AVE 90035
Certificate Information: 1572 S CARDIFF AVE 90035
- Application / Permit
- 25047-20000-00112
- Plan Check / Job No.
- B25VN02212
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 30' X 10' POOL AND SPA PER STANDARD PLANS.
- Permit Issued
- Issued on 1/29/2025
- Issuing Office
- Current Status
- CofO Issued on 3/12/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/29/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/29/2025 | ARAMIK SHAHMIRZAIAN |
| Issued | 1/29/2025 | APPLICANT |
| Permit Finaled | 3/12/2026 | RICHARD STEINBACH |
| CofO Issued | 3/12/2026 | RICHARD STEINBACH |
| Permit Finaled | 3/12/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Noga Pool And Spa Inc; Lic. No.: 946647-C53 | 5739 KANAN ROAD #639 AGOURA HILLS, CA 91301 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 3/19/2025 | Corrections Issued | ASHLEY THOMPSON |
| Pre-Gunite | 3/20/2025 | Corrections Issued | ASHLEY THOMPSON |
| Special/Order Compliance | 3/20/2025 | Partial Inspection | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 3/25/2025 | Approved | ARAM AVEDISIAN |
| Grounding or Bonding | 3/25/2025 | Partial Approval | ARAM AVEDISIAN |
| Pool Piping | 3/25/2025 | Partial Approval | ARAM AVEDISIAN |
| Pre-Gunite | 3/25/2025 | Approved | ARAM AVEDISIAN |
| Deputy Shotcrete | 3/28/2025 | Conditional Approval | DAVID FEILER |
| Grounding or Bonding | 4/11/2025 | Corrections Issued | ASHLEY THOMPSON |
| Grounding or Bonding | 4/21/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Grounding or Bonding | 4/22/2025 | Conditional Approval | STEPHANIE SWANSON |
| Gas Piping or Gas Test | 10/22/2025 | Approved | ASHLEY THOMPSON |
| Enclosure/Fence | 1/15/2026 | Corrections Issued | ASHLEY THOMPSON |
| Enclosure/Fence | 1/30/2026 | Approved | WILBER ROSALES |
| Equipment Noise Level | 2/25/2026 | Approved | JUAN ESCOTO DELGADO |
| Final | 2/25/2026 | Corrections Issued | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 2/25/2026 | SGSOV Approved | ASHLEY THOMPSON |
| Final | 3/11/2026 | Conditional Approval | ASHLEY THOMPSON |