880 N TEAKWOOD ROAD 90049

Certificate Information: 880 N TEAKWOOD ROAD 90049

Application / Permit
25047-20000-00061
Plan Check / Job No.
B25VN01184
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
PROPOSED REMODEL OF EX SWIMMING POOL - DEMO PORTION OF EX SWIMMING POOL TO RESHAPE, REPLASTER, ADD NEW 9'-0" x 9'-0" SPA & BAJA INSIDE EX POOL SHELL, RAISE BOND BEAM AROUND THE NEW SPA AND RAISE THE BOTTOM OF POOL TO 5' DEPTH. ALL WORK PER STD PLAN #268 & SUPPL ENGR DETAILS.
Permit Issued
Issued on 2/10/2025
Issuing Office
Valley
Current Status
CofO Issued on 4/11/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/17/2025 APPLICANT
Assigned to Plan Check Engineer 1/24/2025 HAYATO TSUCHIYA
Corrections Issued 1/25/2025 HAYATO TSUCHIYA
Building Plans Picked Up 1/28/2025 APPLICANT
Plan Check Approved 2/7/2025 GIOVANNY CHAVEZ
Issued 2/10/2025 APPLICANT
CofO in Progress 4/8/2026 KEVIN SARGSYAN
Permit Finaled 4/11/2026 RICHARD STEINBACH
CofO Issued 4/11/2026 RICHARD STEINBACH
Permit Finaled 4/11/2026 RICHARD STEINBACH

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Deluxe Pool Inc; Lic. No.: 1076199-C53 P O BOX 572276      TARZANA, CA 91357
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/8/2025 Approved KEVIN SARGSYAN
Gas Piping or Gas Test 4/8/2025 Corrections Issued KEVIN SARGSYAN
Grounding or Bonding 4/8/2025 Partial Approval KEVIN SARGSYAN
Pool Piping 4/8/2025 Approved KEVIN SARGSYAN
Pre-Gunite 4/8/2025 Conditional Approval KEVIN SARGSYAN
Rough-Electrical 4/8/2025 Approved KEVIN SARGSYAN
Rough-Plumbing 4/8/2025 Approved KEVIN SARGSYAN
Grounding or Bonding 10/20/2025 Corrections Issued KEVIN SARGSYAN
Grounding or Bonding 10/21/2025 Approved KEVIN SARGSYAN
Grounding or Bonding 11/12/2025 Approved MEL KHACHATOURIAN
Enclosure/Fence 1/22/2026 Corrections Issued KEVIN SARGSYAN
Enclosure/Fence 1/27/2026 Not Ready for Inspection KEVIN SARGSYAN
Enclosure/Fence 1/30/2026 Approved KEVIN SARGSYAN
Pool Equipment Noise Test 2/9/2026 Approved EUSEBIO GUZMAN
SGSOV-Seismic Gas S/O Valve 2/17/2026 SGSOV Not Ready MICHAEL ALLEN
Final 3/26/2026 Corrections Issued KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 3/26/2026 SGSOV Approved KEVIN SARGSYAN
Final 4/8/2026 OK to Issue CofO KEVIN SARGSYAN