809 N BRAMBLE WAY 90049
Certificate Information: 809 N BRAMBLE WAY 90049
- Application / Permit
- 25047-10000-01761
- Plan Check / Job No.
- B25LA54152
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- EPLAN. New 16'x35' pool and spa with pool equipment below deck. Foundation and Grading approved and issued under: 24016-10000-38222 and 24030-10000-07684 Grading Work Description includes New Pool
- Permit Issued
- Issued on 2/4/2026
- Issuing Office
- Current Status
- Issued on 2/4/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/23/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2025 | ARSALAN SHABESTARI |
| Assigned to Zoning Architect | 1/2/2026 | LY CHEA |
| Corrections Issued | 1/13/2026 | ARSALAN SHABESTARI |
| Quality Review Completed | 1/19/2026 | ARMEN JIVALAGIAN |
| Plan Check Approved | 2/4/2026 | ARSALAN SHABESTARI |
| Issued | 2/4/2026 | APPLICANT |
Permit Application Clearance Information
| Miscellaneous | Cleared | 1/13/2026 | DAVID URITA |
| Zoning Plan Check | Cleared | 2/3/2026 | LY CHEA |
Contact Information
| Contractor | Luxe Development Inc; Lic. No.: 993473-B | 329 N WETHERLY DR #204 BEVERLY HILLS, CA 90211 |
| Engineer | Kile,, Johnny C; Lic. No.: NA92658 | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Other (see comments) | 2/10/2026 | Conditional Approval | JUAN VALENZUELA |
| Deputy Other (see comments) | 3/3/2026 | Approved | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 3/3/2026 | Partial Approval | KEVIN SARGSYAN |
| Deputy Other (see comments) | 3/4/2026 | Conditional Approval | KEVIN SARGSYAN |
| Deputy Other (see comments) | 3/17/2026 | Approved | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 3/17/2026 | Partial Approval | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 3/19/2026 | Partial Approval | KEVIN SARGSYAN |
| Deputy Other (see comments) | 3/25/2026 | Conditional Approval | DAVID FEILER |
| Deputy Other (see comments) | 4/7/2026 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 4/8/2026 | Corrections Issued | KEVIN SARGSYAN |
| Rough-Plumbing | 4/8/2026 | Not Ready for Inspection | KEVIN SARGSYAN |
| Deputy Shotcrete | 4/9/2026 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 4/13/2026 | Partial Approval | KEVIN SARGSYAN |
| Rough-Plumbing | 4/13/2026 | Partial Approval | KEVIN SARGSYAN |
| Deputy Shotcrete | 4/14/2026 | Conditional Approval | JUAN VALENZUELA |