4123 S CLOVERDALE AVE 90008
Certificate Information: 4123 S CLOVERDALE AVE 90008
- Application / Permit
- 25047-10000-01467
- Plan Check / Job No.
- B25LA45656
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- eplan New 12' x 22' Pool and Spa. All work per std detail 268 and engineer details.
- Permit Issued
- Issued on 11/10/2025
- Issuing Office
- Current Status
- Issued on 11/10/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/30/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 11/3/2025 | NAREG ATARIAN |
| Corrections Issued | 11/4/2025 | NAREG ATARIAN |
| Plan Check Approved | 11/7/2025 | NAREG ATARIAN |
| Issued | 11/10/2025 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 11/3/2025 | JONATHAN HOM |
Contact Information
| Contractor | O C Poolscapes Inc; Lic. No.: 1061813-C53 | , |
| Contractor | Oc Poolscapes Inc; Lic. No.: 1061813-C53 | , |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/2/2025 | Corrections Issued | LUIS CASTRO |
| Gas Piping or Gas Test | 12/2/2025 | Approved | LUIS CASTRO |
| Green Building Rough | 12/2/2025 | Not Ready for Inspection | LUIS CASTRO |
| Pre-Gunite | 12/2/2025 | Corrections Issued | LUIS CASTRO |
| Rough-Electrical | 12/2/2025 | Approved | LUIS CASTRO |
| Rough-Plumbing | 12/2/2025 | Approved | LUIS CASTRO |
| Enclosure/Fence | 3/4/2026 | Not Ready for Inspection | LUIS CASTRO |
| Enclosure/Fence | 3/11/2026 | Conditional Approval | LUIS CASTRO |
| Enclosure/Fence | 3/20/2026 | Approved | LUIS CASTRO |
| Grounding or Bonding | 3/20/2026 | Corrections Issued | LUIS CASTRO |
| Excavation/Setback/Form/Re-Bar | 6/5/2026 | Approved | RAUL BARAJAS |
| Final | 6/5/2026 | Corrections Issued | RAUL BARAJAS |
| Green Building Final | 6/5/2026 | Approved | RAUL BARAJAS |
| Green Building Rough | 6/5/2026 | Approved | RAUL BARAJAS |
| Pre-Gunite | 6/5/2026 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 6/5/2026 | SGSOV Approved | RAUL BARAJAS |
| Equipment Noise Level | 6/9/2026 | Approved | BRIAN CHRISTIAN |
| Final | 6/11/2026 | Conditional Approval | LUIS CASTRO |