933 N AMALFI DR 90272
Certificate Information: 933 N AMALFI DR 90272
- Application / Permit
- 25047-10000-01187
- Plan Check / Job No.
- B25LA37825
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- ePlan: New Pool and Spa ***1 of 2***
- Permit Issued
- Issued on 10/16/2025
- Issuing Office
- Current Status
- Issued on 10/16/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/10/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/12/2025 | CAROLEAN BASMA |
| Plan Check Approved | 9/16/2025 | CAROLEAN BASMA |
| Issued | 10/16/2025 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | O C Poolscapes Inc; Lic. No.: 1061813-C53 | , |
| Contractor | Oc Poolscapes Inc; Lic. No.: 1061813-C53 | , |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Piping or Gas Test | 11/25/2025 | Corrections Issued | KEVIN SARGSYAN |
| Pre-Gunite | 11/25/2025 | Conditional Approval | KEVIN SARGSYAN |
| Rough-Electrical | 11/25/2025 | Partial Approval | KEVIN SARGSYAN |
| Rough-Plumbing | 11/25/2025 | Partial Approval | KEVIN SARGSYAN |
| Gas Piping or Gas Test | 2/10/2026 | Corrections Issued | HERBERT GIRON |
| Rough-Electrical | 2/10/2026 | Corrections Issued | HERBERT GIRON |
| Rough-Plumbing | 2/10/2026 | Not Ready for Inspection | HERBERT GIRON |
| Pool Piping | 3/3/2026 | Approved | HERBERT GIRON |
| Gas Piping or Gas Test | 3/5/2026 | Approved | HERBERT GIRON |
| Rough-Electrical | 3/5/2026 | Approved | HERBERT GIRON |
| Enclosure/Fence | 3/18/2026 | Corrections Issued | HERBERT GIRON |
| Enclosure/Fence | 3/31/2026 | Approved | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 6/10/2026 | Approved | HERBERT GIRON |
| Final | 6/10/2026 | Corrections Issued | HERBERT GIRON |
| Pre-Gunite | 6/10/2026 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 6/10/2026 | SGSOV Approved | HERBERT GIRON |