7419 S ALVERSTONE AVE 90045
Certificate Information: 7419 S ALVERSTONE AVE 90045
- Application / Permit
- 25047-10000-01022
- Plan Check / Job No.
- B25LA33023
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW POOL AND SPA STD#268
- Permit Issued
- Issued on 8/27/2025
- Issuing Office
- Current Status
- CofO Issued on 3/6/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/8/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/8/2025 | JOHN MESIAS |
| Corrections Issued | 8/8/2025 | JOHN MESIAS |
| Issued | 8/27/2025 | APPLICANT |
| CofO in Progress | 3/6/2026 | ANTHONY EGSON |
| Permit Finaled | 3/6/2026 | RICHARD STEINBACH |
| CofO Issued | 3/6/2026 | RICHARD STEINBACH |
| Permit Finaled | 3/6/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 8/27/2025 | TINA MIRANDA |
| Grading Pre-Inspection | Cleared | 8/27/2025 | JOHN MESIAS |
Contact Information
| Contractor | Intex Design And Construction Oc Inc; Lic. No.: 1073000-B | 4000 MACARTHUR BLVD SUITE 600 EAST TOWER #6005 NEWPORT BEACH, CA 92660 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/8/2025 | Corrections Issued | RUBEN RIVAS |
| Gas Piping or Gas Test | 10/8/2025 | Corrections Issued | RUBEN RIVAS |
| Rough-Plumbing | 10/8/2025 | Not Ready for Inspection | RUBEN RIVAS |
| Gas Piping or Gas Test | 10/27/2025 | Corrections Issued | RUBEN RIVAS |
| Pre-Gunite | 10/31/2025 | Approved | RUBEN RIVAS |
| Rough-Electrical | 10/31/2025 | Approved | RUBEN RIVAS |
| Rough-Plumbing | 10/31/2025 | Approved | RUBEN RIVAS |
| Deputy Shotcrete | 11/5/2025 | Conditional Approval | DAVID FEILER |
| Grounding or Bonding | 12/11/2025 | Approved | ANTHONY EGSON |
| Enclosure/Fence | 1/15/2026 | Approved | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 1/29/2026 | Approved | ANTHONY EGSON |
| Final | 1/29/2026 | Not Ready for Inspection | ANTHONY EGSON |
| Pool Equipment Noise Test | 1/29/2026 | Not Ready for Inspection | EUSEBIO GUZMAN |
| SGSOV-Seismic Gas S/O Valve | 1/29/2026 | SGSOV Not Ready | ANTHONY EGSON |
| Equipment Noise Level | 2/3/2026 | Approved | EUSEBIO GUZMAN |
| Final | 2/4/2026 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 2/4/2026 | SGSOV Not Ready | ANTHONY EGSON |
| Final | 2/9/2026 | Not Ready for Inspection | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 2/9/2026 | SGSOV Not Ready | JESUS PINEDA |
| Final | 2/13/2026 | Off-Hour Fees Due | |
| Final | 2/14/2026 | Off-Hour Fees Due | |
| SGSOV-Seismic Gas S/O Valve | 2/18/2026 | SGSOV Not Ready | ANTHONY EGSON |
| ELECTRICAL-Final | 2/25/2026 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 2/25/2026 | SGSOV Approved | ANTHONY EGSON |
| Final | 3/6/2026 | OK to Issue CofO | ANTHONY EGSON |