1902 N ROSCOMARE ROAD 90077

Certificate Information: 1902 N ROSCOMARE ROAD 90077

Application / Permit
25047-10000-00997
Plan Check / Job No.
B25LA32428
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
ePlan: new Pool per starndard plan #268 "COMPLY WITH DEPARTMENT ORDER effective date 10/10/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 11/12/2025
Issuing Office
Current Status
CofO Issued on 4/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/7/2025 APPLICANT
Assigned to Plan Check Engineer 8/11/2025 MOHAMMAD ESMAILI
Corrections Issued 8/12/2025 MOHAMMAD ESMAILI
Applicant returned to address corrections 9/4/2025 MOHAMMAD ESMAILI
Plan Check Approved 11/8/2025 MOHAMMAD ESMAILI
Issued 11/12/2025 APPLICANT
CofO in Progress 4/7/2026 CHRISTOPHER WILSON
Permit Finaled 4/9/2026 RICHARD STEINBACH
CofO Issued 4/9/2026 RICHARD STEINBACH
Permit Finaled 4/9/2026 RICHARD STEINBACH

Permit Application Clearance Information

Construction within easement Cleared 11/4/2025 RIDWAN HARDY

Contact Information

Contractor O C Poolscapes Inc; Lic. No.: 1061813-C53       ,
Contractor Oc Poolscapes Inc; Lic. No.: 1061813-C53       ,
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Piping or Gas Test 12/1/2025 Approved SEAN HAUPT
Pre-Gunite 12/1/2025 Approved SEAN HAUPT
Rough-Electrical 12/1/2025 Approved SEAN HAUPT
Rough-Plumbing 12/1/2025 Approved SEAN HAUPT
Deputy Other (see comments) 12/2/2025 Conditional Approval ANDREW NAVE
Deputy Shotcrete 12/2/2025 Conditional Approval ANDREW NAVE
Enclosure/Fence 1/21/2026 Not Ready for Inspection CHRISTOPHER WILSON
Enclosure/Fence 1/27/2026 Corrections Issued CHRISTOPHER WILSON
Enclosure/Fence 2/10/2026 Approved CARLOS MATAMOROS
Final 3/2/2026 Corrections Issued CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 3/2/2026 SGSOV Not Ready CHRISTOPHER WILSON
Final 3/13/2026 Corrections Issued CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 3/13/2026 SGSOV Not Ready CHRISTOPHER WILSON
Final 3/17/2026 Not Ready for Inspection CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 3/17/2026 SGSOV Approved CHRISTOPHER WILSON
Final 4/1/2026 OK to Issue CofO CHRISTOPHER WILSON